A project has several activities. These activities are shown in the table below, together with their time estimates (in weeks) and the crashing costs information:
Activity Normal Time Normal Cost Crash Time Crash Cost Immediate PredecessorsA 2 $50 1 $70 ---B 4 $80 2 $160 AC 8 $70 4 $110 AD 6 $60 5 $80 AE 7 $100 6 $130 BF 4 $40 3 $100 DG 5 $100 4 $150 C, E, F
A. What is the critical path when normal activities are used?
B. Evaluate the minimum total direct cost for each of the following project durations (based on the cost associated with each activity): 13, 14, 15, 16, 17, and 18 weeks.
The market value of the unlevered equity for this project is closest to?
List key stages of a typical procurement cycle
Describe your role as well as the purpose and results of the project.
Summarize the purpose of the Project Management Institute and provide your thoughts on the PMI methodology and the five phases of the project.
Risk management is an important factor in SaveWithUs' effective use of technology.
What are the possible implications of this change request? What is one of the basic tools for managing changes?
On May 18, of last year, Carter sells unlisted stock with a cost of $24,000 for $60,000. Carter collects $20,000 initially and is scheduled to receive $10,000 each year for four years starting this year plus an acceptable rate of interest.
Prepare strategy for stakeholder communication, participation and consultation and High Risk Hazards
The sales manager is always focusing on how to improve customer service. Initiate periodic upgrades based on current trends.
Explain the rationale behind time and cost estimation methods and why you would chose one method over another.
What do you realize by term "trade-off"
If the firm is in the 40 percent marginal tax bracket, determine the annual net cash flows generated by the drill press.
Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!
whatsapp: +1-415-670-9521
Phone: +1-415-670-9521
Email: [email protected]
All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd