What is the critical path for the project

Assignment Help Project Management
Reference no: EM13965731

ZUMA Part 1

The ARC Company specializes in developing and selling a wide range of high-quality scooters. Sales representatives report that there is a growing demand for racing scooters. ARC's president, Robin Lane, is excited about the possibilities and predicts that one day these kinds of razor scooters will be featured in X-Game events. ARC is a small company and uses a strong matrix to optimally utilize limited manpower.

The Project Priority Matrix for the Red Zuma Project is:


Time Scope Cost
Constrain
X
Enhance X

Accept

X

Part 1

You are a member of a project team assigned to develop the new razor scooter code named "Red Zuma." Table A2.5 contains the information necessary to create a project schedule. For the purpose of this case assume the following:

TABLE A Red Zuma: Project Schedule

ID

Task Name

Duration

Predecessors

 1

1 Red Zuma Project

260 days

 

 2

1.1 Market Analysis

 25 days

 

 3

1.2 Product Design

 30 days

2

 4

1.3 Manufacturing Study

 20 days

2

 5

1.4 Product Design Selection

 10 days

3, 4

 6

1.5 Detailed Marketing Plan

 15 days

5

 7

1.6 Manufacturing Process

 30 days

5

 8

1.7 Detailed Product Design

 45 days

5

 9

1.8 Build Prototypes

 25 days

8

10

1.9 Lab Test Prototypes

 10 days

9

11

1.10 Field Test Prototypes

 15 days

9

12

1.11 Finalized Product Design

 20 days

7,10,11

13

1.12 Final Manufacturing Process

 10 days

12

14

1.13 Order Components

 7 days

12

15

1.14 Order Production Equipment

 14 days

13

16

1.15 Install Production Equipment

 35 days

14FS+20 days, 15FS+30 days

17

1.16 Celebrate

 1 days

6, 16

Note: FS refers to a Finish-to-Start lag.

1. The project begins January 2, 2015.

2. The following holidays are observed: January 1, Martin Luther King Day (third Monday in January), Memorial Day (last Monday in May), July 4th, Labor Day (first Monday in September), Thanksgiving Day (4th Thursday in November), December 25.

3. If a holiday falls on a Saturday, then Friday will be given as an extra day off, and if it falls on a Sunday, then Monday will be given as a day off. If December 25th falls on a Friday then Monday will not be given a day off.

4. The project team works eight-hour days, Monday through Friday.

Construct a network schedule for this project and prepare a memo that answers the following questions:

1. When is the project estimated to be completed? How long will the project take?

2. What is the critical path for the project?

3. Which activity has the greatest amount of slack?

4. How sensitive is this network?

5. Identify two sensible milestones and explain your choices.

Include the following printouts:

• A Gantt chart.
• A network diagram highlighting the critical path.
• A schedule table reporting ES, LS, EF, LF, and slack for each activity.

Verified Expert

Delivery Specification : A Gantt chart. A network diagram highlighting the critical path. A schedule table reporting ES, LS, EF, LF, and slack for each activity. For zuma blue project and also attached screenshot of all diagrams and files.

Reference no: EM13965731

Questions Cloud

Apply theory and concepts of bid process : The response requires at minimum three typed pages with 1 ½ spacing and 12 pt Times Roman font. Please do not demonstrate comprehension use your space to apply that theory and concepts
What is the difference between arbitrary and natural levels : What is the difference between arbitrary and natural levels? Why do these matter? How do archaeologists recover the smallest artifacts and ecofacts?
Explain the principles of interpersonal communications : Explain the principles of and barriers to effective interpersonal communications. Why do the principles matter? How can your couple or group of co-workers overcome the barriers you have listed
Secure all the lease agreement : Please form a corporation (four shareholders) to buy an existing lounge/club. This restaurant is located in San Francisco. The restaurant serves finger food, and makes 90% of its profit by selling alcohol. Also, please make sure you secure all the le..
What is the critical path for the project : Construct a network schedule for project and prepare a memo - What is the critical path for the project and which activity has the greatest amount of slack?
Organizational newcomers or new employees : What ways do mentors help organizational newcomers or new employees?
What is the service level : EcoTable is a retailer of specialty organiz and ecologically friendly foods. In one of their Cambridge, Massachusetts, stores, they plan to offer a gift basket of Tanzanian teas for the holidays season. The gift basket sells for $47, the purchase cos..
Language of international or global business : Should English or Mandarin be the language of international business? If not, what language should be the language of international or global business? Also, why is it important to develop a skill in a foreign language? Discuss...
Five stages of tribal development : Please think of an example of a group or organization that you believe exemplifies one of the five stages of tribal development. This could be from your own experience or from your reading. Explain why you believe this organization or sub-organizatio..

Reviews

Write a Review

Project Management Questions & Answers

  Create a project schedule and align resources

Create a project schedule and align resources, Analyze project schedule and resource allocation

  Managerial roles and gap analysis

Write a report on Managerial Roles and Gap Analysis

  Questionaire on project management

Questionaire on Project Management

  Describe the market growth rate for product

Describe the market growth rate for product and service.

  Prepare a work plan and project schedule - gantt chart

Design an online system for the human resources department to manage available job positions.

  Project risk management approach

How does a project risk management approach pro-vide an early warning signal for impending problems or issues

  Black-scholes options pricing model

Calculate the payoff and the profits for investments

  Describe the features or characteristics of product

Describe the features or characteristics of your product or service.

  Write paper on inventory management system

Write paper on Inventory Management System.

  Analysis of the overall project risk

Analysis of the overall project risk

  Investment and performance analysis

Evaluate the usefulness of ROCE

  Distribution strategy and project management

Distribution strategy and project management

Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd