What is the critical path for the project

Assignment Help Project Management
Reference no: EM133276626

CASE 2.2

The Ellis-Don Company is preparing a bid to build the new 47,000-seat Toronto FC soccer stadium. The construction must start on June 10, 2023, and be completed in time for the start of the 2026 season. A penalty clause of $500,000 per day of delay beyond April 3rd is written into the contract.

Percival Young, the president of the company, expressed optimism at obtaining the contract and revealed that the company could net as much as $5 million on the project. He also said that if they were successful, the prospects of future projects would be bright, since there is a projected renaissance in building classic ball parks with modern luxury boxes.

Technical Details for the Toronto FC Soccer Stadium

The soccer stadium is an outdoor structure with a retractable roof. The project begins with clearing the site, an activity that lasts 60 days. Once the site is clear, work can start simultaneously on the structure itself and demolition of an adjacent building site. This demolition is necessary to start a construction stage for storing materials and equipment. It will take 30 days to demolish the buildings and another 30 days to set up the construction site.

The work on the stadium begins by driving 160 support pilings, which will take 120 days. Next comes the pouring of the lower concrete bowl (120 days). Once this is done and the construction site has been set up, then the pouring of the main concourse (120 days), installation of the playing field (90 days), and construction of the upper steel bowl can occur (120 days).

Once the concourse and upper bowl are completed, work can start simultaneously on building the luxury boxes (90 days), installing the seats (140 days), installing the Jumbotron (30 days), and installing the stadium infrastructure (120 days), which includes bathrooms, lockers, restaurants, etc. Once the seats are installed, then the steel canopy can be constructed (75 days), followed by installation of the lights (30 days). The retractable roof represents the most significant technical challenge to the project. Building the roof track supports (90 days) can begin after the lower concrete bowl is constructed. At this time the dimensions of the roof can be finalized and the construction of the roof at a separate site can begin (180 days). After the roof supports are completed, then the roof tracks can be installed (90 days). Once the tracks and roof are completed, then the roof can be installed and made operational (90 days). Once all activities are completed, it will take 20 days to inspect the stadium.

For purposes of this case assume the following:

The following holidays are observed: January 1, Family Day (third Monday in February), Victoria Day (third Monday in May), Canada Day (July 1st), Labor Day (first Monday in September), Thanksgiving Day (second Monday in October), December 25 and 26.

If a holiday falls on a Saturday, Friday will be given as an extra day off, and if it falls on a Sunday, Monday will be given as a day off.

Given the information provided in the table above, construct a network schedule for the stadium project and answer the following questions:

Question 1. Can the project be completed by the April 3rd, 2026 deadline? How long will it take?

Question 2. What is the critical path for the project?

Question 3. Based on the schedule, would you recommend that Ellis-Don pursue this contact? Why?

Reference no: EM133276626

Questions Cloud

What is the importance of conducting the top-down approach : What is the importance of conducting the top-down approach ( economic-industrial-company) in analyzing common stocks?
Analyze the information and comment : BUS 433 Seneca College analyze the information and comment on what you perceive to be the firm's current strategy or strategies and explain your reasoning
What specific policy you choose to stimulate the economy : The economy is not performing to its fullest potential. What specific policy would you choose to stimulate the economy
What is the role of audit committee in the company : Do companies need to comply with SEC Code? Why or why not? What is the role of Audit Committee in the company?
What is the critical path for the project : BUS1 Fanshawe College Can the project be completed by the April 3rd, 2026 deadline? How long will it take and What is the critical path for the project
Produce a well-organized, cost, and pricing report : BUSINESS 404 Sault College Produce a well-organized, cost, and pricing report that reflects both descriptive and analytical abilities. Consider options
What is the likely demand for the product : What is the likely demand for the product? What impact would the new product probably have on total sales, profits, market share, and return on investment
Based on heavy fumes exhausting recommendations : Case study: Volkswagen Scandal based on heavy fumes exhausting Recommendations and Implementation.
Identify the market equilibrium on price and quantity : Identify the market equilibrium on price and quantity for your chosen country or international firm. Analyze the relevance to real-life applications

Reviews

Write a Review

Project Management Questions & Answers

  Create a project schedule and align resources

Create a project schedule and align resources, Analyze project schedule and resource allocation

  Managerial roles and gap analysis

Write a report on Managerial Roles and Gap Analysis

  Questionaire on project management

Questionaire on Project Management

  Describe the market growth rate for product

Describe the market growth rate for product and service.

  Prepare a work plan and project schedule - gantt chart

Design an online system for the human resources department to manage available job positions.

  Project risk management approach

How does a project risk management approach pro-vide an early warning signal for impending problems or issues

  Black-scholes options pricing model

Calculate the payoff and the profits for investments

  Describe the features or characteristics of product

Describe the features or characteristics of your product or service.

  Write paper on inventory management system

Write paper on Inventory Management System.

  Analysis of the overall project risk

Analysis of the overall project risk

  Investment and performance analysis

Evaluate the usefulness of ROCE

  Distribution strategy and project management

Distribution strategy and project management

Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd