What is the critical path for the project

Assignment Help Operation Management
Reference no: EM131884028

Greendale Stadium Case

The G&E Company is preparing a bid to build the new 47,000 seat Greendale baseball stadium. The construction must start July 1, 2011, and be completed in time for the start of the ?014 season. A penalty clause of S100,000 per day of delay beyond May 20, 2014, is written into the contract.

Ben Keith, the president of the company, expressed optimism at obtaining the contract and revealed that the company could net as much as S2 million on the project. He also said if hey are successful, the prospects for future projects are quite good since there is a projected renaissance in building classic ball parks with modem luxury boxes.

ASSIGNMENT

Given the information provided in Table 6.3, construct a network schedule for the stadium project and answer the following questions:

1. Will the project be able to be completed by the May 20 deadline? How long will it take?

2. What is the critical path for the project?

3. Based on the schedule would you recommend that G&E pursue this contact? Why? Include a one-page Gantt chart for the stadium schedule.

TABLE 6.3

Greendale Stadium Case

 

 

ID

Activity

Duration

Predecessor(s)

1

Baseball Stadium

 

 

2

Clear stadium site

70 days

-

3

Demolish building

30 days

2

4

Set up construction site

70 days

3

5

Drive support piling

120 days

2

6

Pour lower concrete bowl

120 days

5

7

Pour main concourse

120 days

3,6

8

Install playing field

90 days

3,6

9

Construct upper steel bowl

120 days

3,6

10

Install seats

140 days

7,9

11

Build luxury boxes

90 days

7,9

12

Install jumbotron

30 days

7,9

13

Stadium infrastructure

120 days

7,9

14

Construct steel canopy

75 days

10

15

Light installation

30 days

14

16

Build roof supports

90 days

6

17

Construct roof

180 days

16

18

Install roof tracks

90 days

16

19

Install roof

90 days

17,18

20

Inspection

20 days

8,11,13,15,19

The work on the stadium begins by driving 160 support pilings, which will take 120 days. Next comes the pouring of the lower concrete bowl (120 days). Once this is done and the construction site has been set up, then the pouring of the main concourse (120 days), the installation of the playing field (90 days), and the construction of the upper steel bowl can occur (120 days).

Once the concourse and upper bowl are completed, work can start simultaneously on building the luxury boxes (90 days), installing the seats (140 days), installing the jumbotron (30 days), and installing stadium infrastructure (120 days) which includes: bathrooms, lockers, restaurants, etc. Once the seats are installed then the steel canopy can be constructed (75 days) followed by the installation of the lights (30 days).

The retractable roof represents the most significant technical challenge to the project. Building the roof track supports (90 days) can begin after the lower concrete bowl is constructed.

At this time the dimensions of the roof can be finalized and the construction of the roof at a separate site can begin (180 days). After the roof supports are completed then the roof tracks can be installed (90 days). Once the tracks and the roof are completed then the roof can be installed and made operational (90 days). Once all activities are completed it will take 20 days to inspect the stadium.

For purposes of this case assume the following:

1. The following holidays are observed: January 1, Memorial Day (last Monday in May), July 4th, Labor Day (first Monday in September), Thanksgiving Day (4th Thursday in November), December 25 and 26.

2. If a holiday falls on a Saturday then Friday will be given as an extra day off, and if it falls on a Sunday then Monday will be given as a day off.

3. The construction crew work Monday through Friday.

Reference no: EM131884028

Questions Cloud

Develop a case that representative of American literature : Develop for me a case that one of them or both are representative of American literature. Make your case and defend it
Define strengths and weaknesses of each research design : Forensic psychology covers a very broad body of knowledge and has many branches. Forensic psychology professionals often choose an area of interest.
The london interbank offered rate : The London Interbank Offered Rate (LIBOR)
What investment can be justified for the new surface : If maintenance costs are the only saving, what investment can be justified for the new surface? Assume interest at 5%.
What is the critical path for the project : Will the project be able to be completed by the May 20 deadline? How long will it take?What is the critical path for the project?
What will be the value in your account at the end of year : You will invest each payment in an account that pays 14 percent. What will be the value in your account at the end of Year 20?
Describe any flaws discovered in the articles : Perhaps more than any other area of psychology, forensic psychology has at its base, an empirical foundation. This is not to say that all forensic psychology.
Create a dialogue concerning local health care challenges : How should a health care leader interface with local, state, or nationally elected officials to create a dialogue concerning local health care challenges?
Design or update the organizations mission statement : Identify and prioritize major problems and goals. Design or update the organization's mission statement (some organizations may do this step first).

Reviews

Write a Review

Operation Management Questions & Answers

  Organization plants in a poor nation

You are visiting one your organization’s plants in a poor nation. You discover a young girl (under the age of 16) is working the factory floor.

  Company makes and sells various products

A company makes and sells various products. Three such products are Brittle, Croner, Dryad. The following Budget/Forecast information is available for the coming year: Establish whether direct labour or materials will be a limiting factor during the ..

  Conducting an important business meeting

You are in a crowded conference room conducting an important business meeting when the ceiling springs a major leak and water falls from the ceiling tiles all over the conference table.

  Screenshot example of a successful result

You can see the Medusa software post a success result in this video. There is also a screenshot example of asuccessful result on page 84 of the textbook.

  Good leaders are typically positive and enthusiastic

Studies indicate that good leaders are typically positive and enthusiastic.

  Find the average lenght of the waiting line lq

Arrivals at a box office in the hour before the show follow the Poisson distribution with lambda = 8 per minute. Servive times follow an expoential distribution with a mean of 6 seconds. Find the average lenght of the waiting line Lq=

  How much of impact does maturity level of the industry

How much of an impact does the "maturity" level of the industry or company have on strategy? How can you be innovative in a mature industry? How can you be conservative in an introductory/rapid growth situation?

  Employee needs affect planning of development programs

How do employee needs affect the planning of development programs? What is the value of training an employee in a number of different jobs done by his or her workgroup, known as multiskilling? What is the advantage to the organization? To the employe..

  Calculate inventory days of supply-cash-to-cash cycle time

calculate the inventory days of supply (IDS). calculate the cash-to-cash cycle time (CCCT). calculate the days of payables outstanding (DPO).

  Harnessing technology and organization

You are the emergency manager in a city that is having a parade. You are concerned about protestors or terrorist attacks because controversial groups are participating. What kind of technology do you want at your disposal to respond to the situation ..

  How the risk of airport terminal rehab affects their job

Create a schema or chart that depicts HRIS needs and possible solutions to ensure they are effective. Which type of quantative model would a car dealership manager most benefit from utilizing when making a decision? Explain why? Prepare a one page su..

  Lisa needed to work on improving group dynamics

All of this was wearing on relationships and there was fighting among the group; Lisa needed to work on improving group dynamics.

Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd