What is the critical path for the project

Assignment Help Operation Management
Reference no: EM131884028

Greendale Stadium Case

The G&E Company is preparing a bid to build the new 47,000 seat Greendale baseball stadium. The construction must start July 1, 2011, and be completed in time for the start of the ?014 season. A penalty clause of S100,000 per day of delay beyond May 20, 2014, is written into the contract.

Ben Keith, the president of the company, expressed optimism at obtaining the contract and revealed that the company could net as much as S2 million on the project. He also said if hey are successful, the prospects for future projects are quite good since there is a projected renaissance in building classic ball parks with modem luxury boxes.

ASSIGNMENT

Given the information provided in Table 6.3, construct a network schedule for the stadium project and answer the following questions:

1. Will the project be able to be completed by the May 20 deadline? How long will it take?

2. What is the critical path for the project?

3. Based on the schedule would you recommend that G&E pursue this contact? Why? Include a one-page Gantt chart for the stadium schedule.

TABLE 6.3

Greendale Stadium Case

 

 

ID

Activity

Duration

Predecessor(s)

1

Baseball Stadium

 

 

2

Clear stadium site

70 days

-

3

Demolish building

30 days

2

4

Set up construction site

70 days

3

5

Drive support piling

120 days

2

6

Pour lower concrete bowl

120 days

5

7

Pour main concourse

120 days

3,6

8

Install playing field

90 days

3,6

9

Construct upper steel bowl

120 days

3,6

10

Install seats

140 days

7,9

11

Build luxury boxes

90 days

7,9

12

Install jumbotron

30 days

7,9

13

Stadium infrastructure

120 days

7,9

14

Construct steel canopy

75 days

10

15

Light installation

30 days

14

16

Build roof supports

90 days

6

17

Construct roof

180 days

16

18

Install roof tracks

90 days

16

19

Install roof

90 days

17,18

20

Inspection

20 days

8,11,13,15,19

The work on the stadium begins by driving 160 support pilings, which will take 120 days. Next comes the pouring of the lower concrete bowl (120 days). Once this is done and the construction site has been set up, then the pouring of the main concourse (120 days), the installation of the playing field (90 days), and the construction of the upper steel bowl can occur (120 days).

Once the concourse and upper bowl are completed, work can start simultaneously on building the luxury boxes (90 days), installing the seats (140 days), installing the jumbotron (30 days), and installing stadium infrastructure (120 days) which includes: bathrooms, lockers, restaurants, etc. Once the seats are installed then the steel canopy can be constructed (75 days) followed by the installation of the lights (30 days).

The retractable roof represents the most significant technical challenge to the project. Building the roof track supports (90 days) can begin after the lower concrete bowl is constructed.

At this time the dimensions of the roof can be finalized and the construction of the roof at a separate site can begin (180 days). After the roof supports are completed then the roof tracks can be installed (90 days). Once the tracks and the roof are completed then the roof can be installed and made operational (90 days). Once all activities are completed it will take 20 days to inspect the stadium.

For purposes of this case assume the following:

1. The following holidays are observed: January 1, Memorial Day (last Monday in May), July 4th, Labor Day (first Monday in September), Thanksgiving Day (4th Thursday in November), December 25 and 26.

2. If a holiday falls on a Saturday then Friday will be given as an extra day off, and if it falls on a Sunday then Monday will be given as a day off.

3. The construction crew work Monday through Friday.

Reference no: EM131884028

Questions Cloud

Develop a case that representative of American literature : Develop for me a case that one of them or both are representative of American literature. Make your case and defend it
Define strengths and weaknesses of each research design : Forensic psychology covers a very broad body of knowledge and has many branches. Forensic psychology professionals often choose an area of interest.
The london interbank offered rate : The London Interbank Offered Rate (LIBOR)
What investment can be justified for the new surface : If maintenance costs are the only saving, what investment can be justified for the new surface? Assume interest at 5%.
What is the critical path for the project : Will the project be able to be completed by the May 20 deadline? How long will it take?What is the critical path for the project?
What will be the value in your account at the end of year : You will invest each payment in an account that pays 14 percent. What will be the value in your account at the end of Year 20?
Describe any flaws discovered in the articles : Perhaps more than any other area of psychology, forensic psychology has at its base, an empirical foundation. This is not to say that all forensic psychology.
Create a dialogue concerning local health care challenges : How should a health care leader interface with local, state, or nationally elected officials to create a dialogue concerning local health care challenges?
Design or update the organizations mission statement : Identify and prioritize major problems and goals. Design or update the organization's mission statement (some organizations may do this step first).

Reviews

Write a Review

Operation Management Questions & Answers

  Book review - the goal

Operations Management is about a book review. Title of the book is "Goal". This book has been written by Dr. Eliyahu Goldartt. The book has been appreciated by many as one of those books which offers an insight into the operations and strategic capac..

  Operational plan in hospitality enterprise

Operational plan pertaining to a hospitality enterprise is given in detail in the solution. The operational plan is an important plan or preparation which gives guidelines regarding the role and responsibilities of each and every operation at all lev..

  Managing operations and information

Recognise the importance of a strategic approach to the development and deployment of organisational information systems. Demonstrate an understanding of the importance of databases and their integration to the organisation's overall information mana..

  A make-or-buy analysis

An analysis of the holding costs, including the appropriate annual holding cost rate.

  Evolution and contributor of operations management

Briefly explain Evolution and contributor of Operations management.

  Functions and responsibilities of an operations manager

A number of drivers of change have transformed the roles, functions and responsibilities of an operations manager over recent years. These drivers have not only been based on technological innovations but also on the need for organisations to develop..

  Compute the optimal order quantity

Compute the Optimal Order quantity of DVD players. Determine the appropriate reorder point.

  Relationship to operations practice in the organisation

Evaluate problems in operations and identify approaches to overcoming them. Critically evaluate operating plans and identify areas for improvement. Justify, implement and evaluate changes to operations in line with modern approaches.

  A make or buy analysis

Develop a report for Figi Fabricating that will address the question of whether the company should continue to purchase the part from the supplier or begin to produce the part itself.

  Prepare a staffing plan

Prepare a staffing plan showing the change of your unit from medical/surgical staffing to oncology staffing.

  Leadership styles in different organizations

Ccompare the effectiveness of different leadership styles in different organizations

  Risk management tools and models

Be able to understand the concept of risk, roles and responsibilities for risk management and risk management tools and models.

Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd