What is the critical path and expected completion time

Assignment Help Operation Management
Reference no: EM13225773

Question 1

A member of a project team that is implementing a new credit card payment process at a bank has direct responsibility to do all of the following EXCEPT:

be sensitive to conflicts between other team members and help resolve them.

ensure that the project has appropriate resources for the job to be completed.

help solve project problems that spill over into areas outside their expertise.

be called upon to share their expertise in credit card payment processes.

Question 2

Mike Multitask has three projects (A, B, and C) that are each four days long. Mike's supervisor suggests that he work first on project A, finish it, then work on project B until it is finished, and then on project C. Mike boldly declares, "My name isn't Multitask for nothing," so he decides to spend one day working on project A, one on B, one on C, then back to project A, and so on. There is no additional start up or shut down time required by splitting the projects this way. What is the difference in average completion time for all three projects when they are managed Mike's way when compared with his supervisor's suggestion?

There is no difference.

Mike's way is 3 days shorter.

Mike's way is 3 days longer.

Mike's way is 9 days longer.

Question 3

Slack time is routinely lost in a network:

at the point where multiple paths exit a common node.

at the point where multiple paths enter a common node.

at the point where the longest activity begins.

at the point where the shortest activity begins.

Question 4

Following are four sets of most optimistic, most likely, and most pessimistic times (in weeks) for an activity. Which one of the four sets will have a mean estimated time equal to the most likely time?

1, 9, 9

1, 5, 9

1, 1, 9

1, 5, 5

Question 5

You are responsible for managing a project with the following activities (times are given in days).

Activity      Expected Time    Immediate Predecessor(s)

A                 3                            ---

B                 6                            ---

C                 2                            ---

D                 5                             A

E                  2                            C

F                   7                            A

G                   4                         B, D, E

what is the critical path and expected completion time for this project?

A - F ; 12 days

A-D-G; 12 Days

B-G; 10 days

C, E, G; 10 days

Question 6

Assuming a beta distribution is being used, if the most pessimistic time for an activity increases by six weeks, what will happen to the expected time for that activity?


It will increase by one week.

It will decrease by one week.

It will increase by six weeks.

It will remain the same.

Question 7

If the sum of the variances on the critical path (and all other network paths) is equal to zero, what is the probability that the project will be completed by its earliest expected completion date?

50 percent

95 percent

100 percent

It cannot be determined.

Question 8

A project is currently scheduled to be finished on its normal earliest completion date. The project manager has the opportunity to earn a bonus if the project can be completed three weeks ahead of schedule. The increase in project direct costs related to crashing activities would be $40,000. Also, project indirect costs are $15,000 per week. What is the smallest bonus that the project manager should accept if he or she wants to avoid increasing overall project costs?

Less than or equal to $5,000

Greater than $5000 but less than or equal to $10,000

Greater than $10,000 but less than or equal to $15,000

Greater than $15,000

Question 9

You are given the following information about activity B:
Normal time = 9 weeks
Crash time = 5 weeks
Cost to crash per week = $2000
Crash cost = $41,000

What will it cost to complete activity B in 6 weeks?

Less than or equal to $34,000

Greater than $34,000 but less than or equal to $36,000

Greater than $36,000 but less than or equal to $38,000

Greater than $38,000

Question 10

You are given the following information about activity F:
Normal time = 16 weeks
Crash time = 10 weeks
Crash cost = $45,000
Cost to crash per week = $2,000

What is the normal cost for activity F?

Greater than or equat to $55,000

Less than $55,000 but greater than or equal to $47,000

Less than $47,000 but greater than or equal to $40,000

Less than $40,000

Reference no: EM13225773

Questions Cloud

The firm instead rents saucepans every period : Consider the pricing problem of Alcoa's cookware division. Suppose that the world last for only two periods, period 1 and period 2. A saucepan last two periods, so that a saucepan that is bought in period 1 can also be used in period 2. Consumers val..
What might happen with business across state lines : Also consider what might happen if there were no UCC in the United States. What might happen with business across state lines?
How did multitechs organization work : How did Multitech's organization work? How does he keep control?
What winding ratio should the transformer have : A 12V-DC power supply that gets it's power from the 110V (RMS) wall outlet needs a transformer as a first step in generating its output. The rectification and regulation stage of the power supply needs an input voltage of 15V (peak)
What is the critical path and expected completion time : What is the difference in average completion time for all three projects when they are managed Mike's way when compared with his supervisor's suggestion and what is the critical path and expected completion time for this project?
Determine the concentration of donor impurity atoms : A silicon sample at T = 300 K contains an acceptor impurity concentration of \(N_{A}\) = 1016 cm-3. Determine the concentration of donor impurity atoms that must be added so that the silicon is n-type and the Fermi energy is 0.20 eV
Define electrons in the new molecular orbitals : The four molecular p orbitals of the four carbon atoms can be lined up parallel in order to create four new molecular orbitals. The electrons in the new molecular orbitals benefit because they are not confined to just one atom.
How would you try to get individual managers : Assume for a moment that you are the HR Manager for a medium size company. How would you try to get individual managers to be more aware of the legal requirements of staffing systems and to take steps to ensure that they themselves engage in legal..
Allied health professional working with an endocrinologist : You are an allied health professional working with an endocrinologist. You have been working with the patient and need to update the doctor on the reason for the patient's visit. Begin describing the patient's concerns.

Reviews

Write a Review

Operation Management Questions & Answers

  How foreman days course could be positively influence

Elucidate the logic as to explain how Foreman's 3-days course could be positively influence Albertson's profitability.

  Define the scope of the business process outsourcing

define the scope of the business process outsourcing transaction and discuss the importance of each in relation to outsourcing

  Name at least two other worker protection laws

Name at least two other worker protection laws. What is unemployment compensation? What is social Security? What is the National Labor Relations Board and what does it regulate?

  What information should be included on an informed consent

What information should be included on an informed consent document (not a consent to release information document) that you would have a client read over and sign at the initial intake session

  What does the math look like

An automobile emissions testing center has six (6) inspectors and tests 50 autos per hour. What does the math look like

  We will focus on strategic planning since

There are three planning horizons, strategic, tactical, and operational. We will focus on strategic planning since the primary responsibility belongs to you

  Discuss the role of hr management in international strategy

Discuss the role of HR management in international strategy with two articles:1- Going beyond hiring, firing and compensation

  Describe the strategic human resource needs

Describe the strategic human resource needs of an organization that you are familiar with against the measurement tools used by staffing. Further, defend the legality of these selection measurement tools.

  What are the implications of that policy from the standpoint

What are the implications of that policy from the standpoints of (a) the development and implementation of global strategies, (b) the control of foreign subsidiaries and (c) the development of managers with significant international experience and..

  Explain how will growth impact fresh connections operation

Explain how will growth impact Fresh Connections' operations. Illustrate what capabilities should Fresh Connections emphasize in its strategy.

  What is the area of feasible soltuion on a graph

what is the area of feasible soltuion on a graph?

  Discuss how these might change in the future and why

Identify two ways that healthcare organizations perform marketing related data capture that do not violate any regulatory stipulations. Analyze and discuss how these might change in the future and why.

Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd