Schedule the following activities using CPM:
Activity Immediate Predecessor Time (weeks)
A -- 5
B A 10
C A 8
D B 6
E C 7
F C 4
G D,E,F 4
a. Draw the network.
b. What is the critical path? Enumerate all the paths in the network.
c. For the cost data shown below, reduce the project completion time by three weeks. Assume a linear cost per week shortened, and show, step by step, how you arrived at your schedule.
Activity Normal time Normal cost Crash time Crash cost
A 5 $7,000 3 $13,000
B 10 12,000 7 16,500
C 8 5,000 7 6,000
D 6 4,000 5 5,000
E 7 3,000 6 6,000
F 4 6,000 3 7,000
G 4 7,000 3 9,000
|
Report of current outbreak
: Determine a news report of a current outbreak or other health crisis (within a month) then search for a peer-reviewed scientific article on the same or closely related topic
|
|
Describe at least two actions a manager can take to protect
: Describe at least two actions a manager can take to protect her- or himself and the organization she or he represents from a tort lawsuit.
|
|
Sufficient evidence to reject the manufacture claim
: Do the sample data present sufficient evidence to reject the manufacture's claim? Test using a a=0.05. What is the p-value of the test.
|
|
Calculate the phenotypic variance
: Assume you wish to increase fruit diameter in tomatoes, and you want to estimate heritability for this trait. You measured the diameter of tomatoes in two inbred lines.
|
|
What is the critical path
: What is the critical path? Enumerate all the paths in the network. For the cost data shown below, reduce the project completion time by three weeks
|
|
Normal distributioin of university admissions test
: Test scores on a university admissions test are normally distributed, with a mean of 500 and a standard deviation of 100. a) What is the probability that a randomly selected applicant scores between 425 and 575?
|
|
Writing a one page proposal consisting
: Need help writing a one page proposal consisting of 300 words about informing people about the air pollution in china.
|
|
Has the new math program been effective
: Construct a control chart for test errors and set the control limits to contain 99.73% of the random variations in test scores. What does the chart tell you? Has the new math program been effective?
|
|
Provide example of an animal species
: Food resources are rarely shared uniformly in the environment. Most vary seasonally or have a patchy distribution and can become locally depleted.
|