1. Schedule the following activities using CPM:

Activity

IMMEDIATE PREDECESSOR

TIME (WEEKS)

A

-

1

B

A

4

C

A

3

D

B

2

E

C, 0

5

F

D

2

G

F

2

H

E, G

3

a. Draw the network.

b. What is the critical path?

c. How many weeks will it take to complete the project?

d. Which activities have slack, and how much?

2. The R&D department is planning to bid on a large project for the development of a new communication system for commercial planes. The accompanying table shows the activi­ties, times, and sequences required:

Activity

IMMEDIATE PREDECESSOR

TIME (WEEKS)

A

-

3

B

A

2

C

A

4

D

A

4

E

B

6

F

C. D

6

G

D. F

2

H

D

3

I

E. G. H

3

a. Draw the network diagram.

b. What is the critical path?

c. Suppose you want to shorten the completion time as much as possible, and you have the option of shortening any or all of B, C, D, and G each one week. Which would you shorten?

d. What is the new critical path and earliest completion time?

3. The following represents a project that should be scheduled using CPM-

Activity

IMMEDIATE PREDECESSORS

TIMES (DAYS)

a

m

b

A

-

1

3

5

B

-

1

2

3

C

A

1

2

3

D

A

2

3

4

E

B

3

4

11

F

C. D

3

4

5

G

D. E

1

4

6

H

F,G

2

4

5

a. Draw the network.

b. What is the critical path?

c. What is the expected project completion time?

d. What is the probability of completing this project within 16 days?

Reference no: EM13735637

Questions Cloud

Entry strategy-technology based-quality based or cost based : Success of a company investing and operating in a foreign country depends on the competitive advantage of the company. The entry strategy could be technology based, quality based, or cost based. Explain and comment.
Compliance with regulatory agency guidelines : As a CMAA in a clinic, you are responsible for ensuring that job performance is in compliance with regulatory agency guidelines. There are many areas of compliance that a CMAA must be familiar with: financial risk, local and state regulations, Occ..
Exit gas streams are at 8 bar and at the same temperature : A gas stream is entering a separator at 1 mole/sec with mole fractions 15% A and 85% B. (Component 1 is A, component 2 is B.) At surface, the gas stream is 8 bar and 350K. Two streams exit the separator, one primarily of A (0.99 A1, 0.01 A2), and one..
Legal establishment of a nuclear family unit : Today, people marry for a variety of reasons, including family obligations, arranged marriages, the legal establishment of a nuclear family unit, the legal protection of children, or the public declaration of commitment. Discuss the following:
What is the critical path : What is the critical path. Suppose you want to shorten the completion time as much as possible, and you have the option of shortening any or all of B, C, D, and G each one week. Which would you shorten
What is significance of brown and board of education : What was the relationship between consumer culture and the emphasis on family life in the postwar era? What is the significance of the Brown v. Board of Education of Topeka decision?
Construct a b+ tree : Construct a B+ tree for the following set of key value (2,3,5,7,11,19,23,29,31) in ascending order where the pointers that will fit in one node is as follows:A. four B. six C. eight assuming the tree is initially empty and values are in ascending ..
Strategic leaders are concerned with vision and mission : A management consultant said that strategic leaders are concerned with vision and mission, while strategic managers are concerned with strategy.
Prepare a sample portfolio with resume : Each student is required to prepare a sample portfolio with (1) resume, (2) letter of interest, (3) sample thank you letter, (4) memo, and (5) sample interview questions and answers

Reviews

Write a Review

Operation Management Questions & Answers

  Book review - the goal

Operations Management is about a book review. Title of the book is "Goal". This book has been written by Dr. Eliyahu Goldartt. The book has been appreciated by many as one of those books which offers an insight into the operations and strategic capac..

  Operational plan in hospitality enterprise

Operational plan pertaining to a hospitality enterprise is given in detail in the solution. The operational plan is an important plan or preparation which gives guidelines regarding the role and responsibilities of each and every operation at all lev..

  Managing operations and information

Recognise the importance of a strategic approach to the development and deployment of organisational information systems. Demonstrate an understanding of the importance of databases and their integration to the organisation's overall information mana..

  A make-or-buy analysis

An analysis of the holding costs, including the appropriate annual holding cost rate.

  Evolution and contributor of operations management

Briefly explain Evolution and contributor of Operations management.

  Functions and responsibilities of an operations manager

A number of drivers of change have transformed the roles, functions and responsibilities of an operations manager over recent years. These drivers have not only been based on technological innovations but also on the need for organisations to develop..

  Compute the optimal order quantity

Compute the Optimal Order quantity of DVD players. Determine the appropriate reorder point.

  Relationship to operations practice in the organisation

Evaluate problems in operations and identify approaches to overcoming them. Critically evaluate operating plans and identify areas for improvement. Justify, implement and evaluate changes to operations in line with modern approaches.

  A make or buy analysis

Develop a report for Figi Fabricating that will address the question of whether the company should continue to purchase the part from the supplier or begin to produce the part itself.

  Prepare a staffing plan

Prepare a staffing plan showing the change of your unit from medical/surgical staffing to oncology staffing.

  Leadership styles in different organizations

Ccompare the effectiveness of different leadership styles in different organizations

  Risk management tools and models

Be able to understand the concept of risk, roles and responsibilities for risk management and risk management tools and models.

Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd