What is the critical path

Assignment Help Business Management
Reference no: EM132819523

The estimated times and immediate predecessors for the activities in a project at John Black's company are given in the following table. Assume that the activity times are independent. All times are in weeks. 

Activity  Predecessors   Optimistic Time (a)  Most Likely Time (m)   Pessimistic Time (b) 

A  --  2  4  6 

B  --  1  2  9 

C  A  2  4  6 

D  B  5  8  17 

E  C  3  4  11 

  1. What is the critical path? You may use any method to determine this.
  2. What is the expected completion time of the project? What is the expected total work time for this project?
  3. What is the probability of completing the project in 16 weeks or longer? 

Reference no: EM132819523

Questions Cloud

Which store offers a better deal : Annual payments of $4,000 beginning next years, also with no finance charge. Assume that the market interest rate is 4%. Which store offers a better deal?
Prepare clinical study in a reference laboratory : A company has a new self tested product for pregnancy that is wishes to CE mark as IVD per Directive 98/79/EC. Which action MUST the company take?
Fertility drugs and ovarian cancer : Stanford University medical researchers conducted a study on the correlation between the use of fertility drugs and ovarian cancer.
Calculate the internal growth rate : Calculate the internal growth rate given the following information: total assets $450,000; net income $100,000; dividends paid $35,000
What is the critical path : The estimated times and immediate predecessors for the activities in a project at John Black's company are given in the following table.
What the cash provided by financing activities is : Dividends paid to preferred shareholders were charged directly to retained earnings. The cash provided by financing activities during 2020 is?
Describe a ritual that occurs in the military : There are many rituals in the military that are highly symbolic such as the Tomb of the Unknowns or the Funeral Flag. These have long and significant histories.
How much cash value will she need to have in the policy : How much cash value will she need to have in the policy so that she will be able to withdraw the $4,000 per month starting on her 75th birthday
What is the expected total annual holding cost plus : What is the expected total annual holding cost plus ordering cost?

Reviews

Write a Review

Business Management Questions & Answers

  Caselet on michael porter’s value chain management

The assignment in management is a two part assignment dealing 1.Theory of function of management. 2. Operations and Controlling.

  Mountain man brewing company

Mountain Man Brewing, a family owned business where Chris Prangel, the son of the president joins. Due to increase in the preference for light beer drinkers, Chris Prangel wants to introduce light beer version in Mountain Man. An analysis into the la..

  Mountain man brewing company

Mountain Man Brewing, a family owned business where Chris Prangel, the son of the president joins. An analysis into the launch of Mountain Man Light over the present Mountain Man Lager.

  Analysis of the case using the doing ethics technique

Analysis of the case using the Doing Ethics Technique (DET). Analysis of the ethical issue(s) from the perspective of an ICT professional, using the ACS Code of  Conduct and properly relating clauses from the ACS Code of Conduct to the ethical issue.

  Affiliations and partnerships

Affiliations and partnerships are frequently used to reach a larger local audience? Which options stand to avail for the Hotel manager and what problems do these pose.

  Innovation-friendly regulations

What influence (if any) can organizations exercise to encourage ‘innovation-friendly' regulations?

  Effect of regional and corporate cultural issues

Present your findings as a group powerpoint with an audio file. In addition individually write up your own conclusions as to the effects of regional cultural issues on the corporate organisational culture of this multinational company as it conducts ..

  Structure of business plan

This assignment shows a structure of business plan. The task is to write a business plane about a Diet Shop.

  Identify the purposes of different types of organisations

Identify the purposes of different types of organisations.

  Entrepreneur case study for analysis

Entrepreneur Case Study for Analysis. Analyze Robin Wolaner's suitability to be an entrepreneur

  Forecasting and business analysis

This problem requires you to apply your cross-sectional analysis skills to a real cross-sectional data set with the goal of answering a specific research question.

  Educational instructional leadership

Prepare a major handout on the key principles of instructional leadership

Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd