You have signed a contract to build a Dog House for Mr. Trumpf. You will receive a $750 bonus for completing the project within 45 days. The cotnract also contains a penalty clause in which you will lose $100 for each day the project takes longer than 45 working days.
Develop a project network given the information below and answer the questions that follow:
Activity Description Predecessor Te (days)
A Pour Foundation None 9
B Erect Frame A 12
C Roof B 12
D Windows B 3
E Doors B 3
F Electrical B 9
G Rough-in Frame C,D,E,F 6
H Door Opener E,F 3
I Paint G,H 6
J Cleanup I 3
1) What is the critical path?
2) Do you expect to get the bonus?
3) If the project took 53 days, how much of a penalty would you pay?
From the choice of simple moving average, weighted moving average, exponentialsmoothing, and linear regression analysis
You are purchasing agent for company that just purchased new accounting and invoicing software system. So what kind of damages might be appropriate in case?
Which of the following element is NOT a part of Quality Principles in Total Quality Management?
Is there a point at which diversity and culture wield too much influence and yield ambiguity and diminished productivity as a result?
How would you characterize IDEO's process, organization, culture, and management?
Every employee of an organization has to find the right relationship between work life and personal life.
International Logistics, Inc. is a conglomerate based in the United States that specializes in the manufacturing and distribution of high tech equipment.
Think about service delivery and how it affects your life. Generate ideas for additional improvements in service delivery for banking, higher education, or health care. You do not have to stick to these fields, they are just suggestions.
The ethical decision-making framework includes the concepts of ethical issue intensity, individual factors, organizational factors, and opportunity. Briefly, discuss how these concepts influence the ethical decision-making process.
Examine systems mapping for operations and supply chain systems. Research the Japanese auto supply chain for its component parts and previous assessment of the system.
What would happen if a new estimate for task D increases its expected duration from two days to six days? Would the project take longer?
Analyze relevant global leadership concerns for the future. Analyze emerging leadership theories that are appropriate for a global agenda. Evaluate the leader's responsibility to prepare the self for work in a competitive, complex, and diverse workpl..
Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!
whatsapp: +1-415-670-9521
Phone: +1-415-670-9521
Email: [email protected]
All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd