IT Project Management Calculations
Assume you have completed three months of the project. The BAC was $200 000 for this six month project. Also assume the following:
PV = $120,000EV = $100,000AC = $90,000
A. What is the cost variance, schedule variance, cost performance index (CPI), and schedule performance index (SPI) for the project?
B. How is the project doing? Is it ahead of schedule or behind schedule? Is it under budget or over budget?
C. Use the CPI to calculate the estimate at completion (EAC) for this project. Is the project performing better or worse than planned?
Process of control schedule and control cost - implement the process of control schedule and control cost. You must state your case and supporting evidence for the need of implementing the process of control schedule and control cost to your stakeh..
Discuss opportunities for improving the quality of service in this situation.
An effective project manager needs a variety of both technical and business skill sets and find the non-technical skills that have been associated with superior project management.
The tax consequences from the sale of the asset will be?
Analyze the role of project management in creating and maintaining facility assets and explain internal factors that affect project management decisions within facilities management of a resort hotel.
What are the six barriers for project success? Give examples of how these barriers might hamper a project.
You have been assigned to a new and important project for your company. How would your management style differ if your project was being done in a functional organization verses a pure project environment?
The Colonial House Furniture Company manufactures two-drawer oak file cabinets that are sold through catalogs.
Compute the internal rate of return for each project.
Find all risks and rate each risk - Select two of the highest risks. Describe why these are considered high risk, and explain their potential effect on the project.
Project planning need only be a one-time exercise in order to get an idea of the project and its major ramifications.
Why is using Bayes' theorem important to help answer health care administration-related questions
Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!
whatsapp: +1-415-670-9521
Phone: +1-415-670-9521
Email: [email protected]
All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd