Reference no: EM132972466
Question - On January 1, 2023, Amelia Company decided to expand operations and had purchased land an old building for construction of new manufacturing plant. The following costs were incurred in purchasing the property and constructing the new building:
Purchase price (the old building has no fair value) 2,500,000
Payment of property taxes on the land for 2022 and 2023 (equally for each year) 100,000
Title search and insurance 50,000
Special assessment for city improvements on water and sewer 150,000
Building permit 30,000
Cost to destroy existing building on the land 60,000
Contract cost of new building 7,000,000
Architect fee 200,000
Sidewalk and parking lot 100,000
Fire insurance on building - 1 year 40,000
Required -
1. What is the cost of the land?
A. 2,860,000 C. 2,800,000
B. 2,810,000 D. 2,750,000
2. What is the cost of the building?
A. 7,440,000
B. 7,290,000
C. 7,390,000
D. 7,330,000