What is the cost of holding one unit of component c

Assignment Help Cost Accounting
Reference no: EM132755067

Problem 1: A firm has used the economic order quantity (EOQ) formula to arrive at an EOQ for Component C1 of 400 units. Annual demand for Component C1 is 12,000 units and the cost of placing an order for the component is $40. What is the cost of holding one unit of Component C1 in inventory for one year?

Reference no: EM132755067

Questions Cloud

Which of the three leadership styles do you considered : Which of the three leadership styles do you considered as most effective? Why? and what do you think are the characteristics of an effective and efficient team
How do make journal entry to record the accrual of interest : Laudie Company issued $400,000 of 9%, Prepare the journal entries to record the accrual of interest on December 31, 2020 events.
Determine and discuss the different challenges : Determine and discuss the different challenges and difficulties experienced by a group or organizations in making decisions.
Communicate with people from diverse cultures : In what specific ways can you enhance your ability to communicate with people fromdiverse cultures?
What is the cost of holding one unit of component c : A firm has used the economic order quantity (EOQ), What is the cost of holding one unit of Component C1 in inventory for one year?
Describe the term time value of money : Describe the term, 'time value of money'? Provide at least three (3) reasons as to why the time value of money is an important concept
Find out the equivalent units for direct materials : Find out the equivalent units for direct materials and conversion costs; cost per equivalent unit for direct materials and conversion costs.
Calculate the range of possible npv values : Calculate the net present value (NPV) for each type of stand under each of the three scenarios. Calculate the range of possible NPV values
Explain the rationale behind the inverse : Explain the rationale behind the inverse relationship between bond prices and market interest rates. A fundamental principle of bond investing

Reviews

Write a Review

Cost Accounting Questions & Answers

  The bank statement included

The bank statement included a $930 credit memo for the collection of a note. The principal of the note was $900, and the interest collected amounted to $30.

  Is the cost of leftover paint transferred

Paint is needed for t-shirt printing service. Is the cost of leftover paint ($160) transferred from order 28 to order 29 a direct cost or indirect cost? Why?

  What is difference between a cost center and a profit center

What is the difference between a cost center and a profit center? What is the difference between a profit center and an investment center? Why is it difficult to assess the effectiveness of discretionary cost centers?

  Prepare an income statement for the year ending

Prepare an income statement for the year ending May 31, 2005 and prepare a retained earnings statement for the year ending May 31, 2005.

  The differences between aasb 8 and the old accounting

Write a report on The differences between AASB 8 and the old accounting standards on segment reporting.

  What amount would be charged to a producing department

What amount would be charged to a producing department that had 1,000 pages of contracts reviewed, made 15 regulatory review requests

  Prepare the adjusting entry needed for business solutions

Prepare the adjusting entry needed for Business Solutions to recognize bad debts expense on March 31, 2012, under each of the following independent assumptions

  Calculate the total dollar amount of supervisions cost

Calculate the total dollar amount of Supervisions cost that would have been allocated to the Shapez product line, if activity-based costing had been used in the last quarter - Calculate the activity-cost driver rate for the Supervisions activity.

  What procedures could be put into place to prevent

What do you suppose caused the discrepancy between the actual count and the count that Rhonda had supplied?

  What forecasting cost at particular level of activity called

What Forecasting a cost at a particular level of activity is called? A cost that has both a fixed and variable component is called a

  Transaction analysis and statements congress authorized the

transaction analysis and statements. congress authorized the flood control commission to start operation on october 1

  What is chicos degree of operating leverage

The firm incurs fixed operating costs of $30,000 and variable operating costs of $12 per unit. What is Chico's degree of operating leverage (DOL) at a base level of sales of 15,000 units?

Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd