What is the construction in progress

Assignment Help Accounting Basics
Reference no: EM132603895

Question - On July 1, 2014, OG obtained a contract to construct a building. The building was estimated to be built at a total cost of P 15,000,000 and is scheduled for completion on October 2016. The contract contains a penalty clause to the effect the other party was to deduct P 35,000 form the contract price for each week of delay. On the other hand, if the contractor was able finish the building earlier than agreed, it will be rewarded an amount equal to P 50,000 for every month of early completion. Furthermore, cost escalation clause was included in the contract. In 2015, the estimated costs of particular construction material amounting to P 520,000 were bought for P 780,000. The increase in the contract price related to this cost escalation was approved by the client.

Year

2014

2015

2016

Costs incurred

P1,750,000

P6,440,000

P1,085,000

Estimated cost to complete

7,000,000

1,810,000

0

Progress billings

1,400,000

15,225,000

4,200,000

REQUIRED -

1. What is the original contract price in 2014?

2. What is the original contract price in 2015?

3. What is the construction in progress, net as of 2015?

Reference no: EM132603895

Questions Cloud

Community health assessments : Community health assessments are used by health planners to identify, and prioritize health problems within a given community.
Stages for developing the organizational change action plan : You have been engaged as an Organizational Development (OD) consultant by an organization with which you have deep familiarity that has endeavored to implement.
What are the costs of implementing a tracking program : Research and analyze workplace monitoring and share what are the costs and benefits of implementing a tracking program? Also, please research and share.
How do calculate federal tax payable : How do Calculate his 2019 federal Tax Payable before consideration of credits. Canadian resident Marcus Alonso has calculated his Taxable Income to be 114,832.
What is the construction in progress : The building was estimated to be built at a total cost of P 15,000,000. What is the construction in progress, net as of 2015
Community-based patient advocacy group : You are working for a community-based patient advocacy group.
What numbers did they look at and why : NY State took certain measures to "flatten the curve," what did they do, why do you think they did those things
Demonstrating an understanding of human resource application : Primary research for this assignment can be in the form of a personal or telephone interview. With COVID-19, please utilize technology to conduct your interview
Description of pharmacy professional activities : description of your Pharmacy professional activities/projects and Pharmacy career goals, brief explanation of how much this award means to you

Reviews

Write a Review

Accounting Basics Questions & Answers

  The zaf radiator company uses a normal -cost accounting

the zaf radiator company uses a normal -cost accounting system with a single manufacturing overhead cost pool and

  Organization incentive plans relate to organizational

Prepare a 700- to 1,050-word paper examining how your organization's incentive plans relate to organizational objectives. Evaluate how the incentives plans do, or do not, help the organization to achieve its goals and objectives.

  Indicate if it is relevant or not to the related decision

The costs listed below relate to a variety of different decision situations.- For each cost listed, indicate if it is relevant or not to the related decision.

  James owns a three-story building

Eviction. James owns a three-story building. He leases the ground floor to Juan's Mexican restaurant. The lease is to run for a five-year period and contains an express covenant of quiet enjoyment.

  Determine the inventory as of december

Determine the inventory as of December 31, 2011, by the lower of cost or market method, applying this method directly to each item

  Wilson co purchased land as a factory site for 900000

wilson co. purchased land as a factory site for 900000. wilson paid 80000 to tear down two buildings on the land.

  Record the journal entry for the issuance of the bonds

On January 1, Year 1 Acorn Financial Corp. issued 800 convertible bonds. Record the journal entry for the issuance of the convertible bonds on January 1, Year 1

  What is george allowable deduction for these expenses

George paid a scalper $200 for the two play tickets with a face value of $80 each. What is George's allowable deduction for these expenses

  Calculate the Ending inventory on a FIFO

Transactions for the month of June were: Assuming that perpetual inventory records are kept in dollars, the Ending inventory on a FIFO basis is

  Calculate how many sausage products you need to sell

Sunshine Valley Meat Company produces one of the best. Calculate how many sausage products you need to sell in order to make $10,000 target profit for the year.

  By what amount would net income differ

By what amount would net income differ if bad debt expense was computed using the percentage-of-receivables approach

  Compute the depreciation expense for the year ended

Compute the depreciation expense for the year ended December 31, 2018. Blue elected to depreciate the building on a straight-line basis

Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd