What is the capacity of the bottleneck

Assignment Help Operation Management
Reference no: EM132465101 , Length: 1 page

Problem 1:

Melissa's Photo Studio offers both individual and group portrait options. The process flow diagram in Figure 5.10 shows that all customers must first register and then pay at one of two cashiers. Then, depending on whether they want a single or group portrait they go to different rooms. Finally, everyone picks up their own finished portrait.

2115_figure.jpg

Part a. How long does it take to complete the entire process for a group portrait?

Part b. What single activity is the bottleneck for the entire process, assuming the process receives equal amounts of both groups and individuals?

Part c. What is the capacity of the bottleneck for both groups and individuals?

Problem 2:

Swenson Saws produces bow, frame, dovetail, and tenon saws used by craft furniture makers. During an 8-hour shift, a saw is produced every 6 minutes. The demand for bow, frame, and dovetail saws is about the same, but the demand for tenon saws is twice the demand for the other three.

If mixed-model scheduling is used, how many of each saw will be produced before the cycle is repeated?

Part a. Determine a satisfactory production sequence for one unit production. How often is this sequence repeated?

Part b. How many of each saw does Swenson produce in one shift?

Reference no: EM132465101

Questions Cloud

Calculate the sensitivity-specificity-positive predictive : Calculate the sensitivity, specificity, and positive predictive value of the test.
Calculate the carrying amount of the investment in bandicoot : Prepare journal entries in the records of Brown Ltd for each of the years ended 30 June 2016 to 2018 in relation to its investment in the associate
Find the sample size necessary for a confidence level : Find the sample size necessary for a 90% confidence level with maximal error of estimate E = 0.25 for the mean price per 100 pounds of watermelon.
Describe the actual versus budget for the timeline : In your role as a Project Manager for Kingston-Bryce Limited you have been assigned to create a scorecard. Now that the acquisition is underway.
What is the capacity of the bottleneck : How long does it take to complete the entire process for a group portrait and What is the capacity of the bottleneck for both groups and individuals
Probability that 3 female students and 2 male students : What is the probability that 3 female students and 2 male students will be selected? Round your answer to 3 decimal places.
On which test did he do better relative to rest of class : He received a score of 70 on a biology test for which the class mean was 70 with standard deviation 3. On which test did he do better relative to the rest.
Describe various tools used in project management : You will develop a project management methodologies and tools FAQ document in Microsoft Word or Excel that evaluates: various tools used in project management.
Calculate the value of x the random variable : Find the value of X, the random variable time taken to assemble that is exceeded 84% of the time.

Reviews

Write a Review

Operation Management Questions & Answers

  Professional maintain positive outlook in their profession

List 3 developmental activities that can help a professional maintain a positive outlook in their profession.

  Human beings are more dissatisfied with unfair process

Research has shown that human beings are more dissatisfied with an unfair process than with an undesirable outcome.

  What are consumer-driven healthcare plans

What are consumer-driven healthcare plans and how do they work? Do you think it would be advantageous to depend on these types of plans instead of the more common employer-defined coverage plans? How about going back to using health insurance for cat..

  How do you position your brand against competitors

What is the most challenging part of creating a positive brand image in the consumer's mind? How do you position your brand against competitors?

  Determine the total cost of strategy

Identify the one time and recurring costs that should be examined to determine the total cost of a strategy.

  Discussing the level of agreement or disagreement

From the e-Activity, discuss your level of agreement or disagreement with the author's view that benevolence and justice make a pair; that is, when benevolence.

  How are planning and control linked

How are planning and control linked. Is the control function linked to the organizing and leading functions of management. Explain

  Prepare the payroll register using the time sheets provided

Prepare the payroll register using the time sheets provided by the management and information can be found on each employee’s history card.

  Elements of communication is most likely to influence

You’ve dreaded it for a while, but now you feel prepared. In 30 minutes you’ll have to terminate Tim, a 12-year employee who is beloved by everyone in the firm. Which of the following elements of communication is MOST likely to influence Tim’s percep..

  Balancing centralized versus distributed processing-control

What are the key issues in balancing centralized versus distributed processing and control?

  Explain what a gap analysis

Explain what a "gap analysis" is including how gaps are defined and measured. Be sure to address how gap analysis relates to needs, requirements, design, project scoping, evaluation and evaluation planning.

  Important to the project manager

Project communication methods including who the stakeholders are and why they are important to the project manager. The use of project quality, including earned value analysis, and examples of successful and troubled projects.

Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd