What is the budgeted materials purchases cost

Assignment Help Managerial Accounting
Reference no: EM132507038

Question 1: A sporting goods manufacturer budgets production of 44,000 pairs of ski boots in the first quarter and 35,000 pairs in the second quarter of the upcoming year. Each pair of boots requires 2 kilograms (kg) of a key raw material. The company aims to end each quarter with ending raw materials inventory equal to 30% of the following quarter's material needs. Beginning inventory for this material is 26,400 kg and the cost per kg is $9. What is the budgeted materials purchases cost for the first quarter?

Multiple Choice

Option 1: $792,000.

Option 2: $743,400.

Option 3: $554,400.

Option 4: $840,600.

Option 5: $1,029,600.

Reference no: EM132507038

Questions Cloud

Build a HUNGRY BUNNY ON A MAGICAL PATH Game : You are required to build a "HUNGRY BUNNY ON A MAGICAL PATH" game that has a Hungry Bunny as main character
What revenue from the two products would be : Assuming Maxim further processes Green Health further into Premium Green and Green Deluxe, revenue from the two products would be
What is the four-year annualized interest rate : The first-year (one-year) interest rate is 22.0%, the second-year one-year rate is 16.0%, the third-year one-year rate is 23.0%, and the fourth-
What is glassmakers pre-merger wacc : The tax rate is 40%. The cost of debt premerger is 11%. The expected market rate of return is 10%. What is Glassmakers' pre-merger WACC?
What is the budgeted materials purchases cost : Beginning inventory for this material is 26,400 kg and the cost per kg is $9. What is the budgeted materials purchases cost for the first quarter?
What maximum price would you pay for a standard : What maximum price would you pay for a standard 4% level-coupon bond (with monthly payments and a face value of $10,000)
What is the value of the firm : If the rd is 12%, the rsU= 16% and the corporate tax rate is 40%, then what is the value of the firm (VL) according to MM with corporate taxes?
What is the npv of the project : Taking into account the costs of external financing, what is the NPV of the project?
Compute the amount of cash received from total sales : the first month after the sale, and the remaining 5% are not collected. Compute the amount of cash received from total sales during the month of May.

Reviews

Write a Review

Managerial Accounting Questions & Answers

  Manage budgets and financial plans

Explain the budgeting process and its importance to a business, identifying the components of different budgets, forecast estimates for inclusion in the budgets.

  Prepare a retained earnings statement

Prepare a retained earnings statement for the year and Prepare a stockholders' equity section of given case.

  Prepare a master budget for the three-month period

Prepare a master budget for the three-month period.

  Construct the companys direct labor budget

Construct the company's direct labor budget for the upcoming fiscal year, assuming that the direct labor workforce is adjusted each quarter to match the number of hours required to produce the forecasted number of units produced.

  Evaluate the predetermined overhead rate

Evaluate the Predetermined Overhead Rate

  Determine the company''s bid

Determine the company's bid if activity-based costing is used and the bid is based upon full manufacturing cost plus 30 percent.

  Compute the pool rates for the different activities

Complete the schedule to compute the pool rates for the different activities.

  Prepare Company financial statements

Prepare Company financial statements

  Prepare an analysis of terracycles

This individual assignment is based on the TerraCycle Inc.

  Discuss the ethical issues

Discuss the ethical issues

  Political resources in emerging markets

Calculate the GDP in Income Approach  and Expenditure Approach

  Management accounting - ehsan electronics company

A new plant accountant suggested that the company may be able to assign support costs to products more accurately by using an activity based costing system that relies on a separate rate for each manufacturing activity that causes support costs.

Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd