Reference no: EM132506852
Gwenllian, Inc. purchased land in 2019. An existing structure was demolished, and a new warehouse was constructed on the property in September of 2019. Gwenllian hired construction workers at a rate of $25 per hour to do the construction work (1,680 hours in total).
Warehouse Construction Cost Data
Purchase price - Land $125,000
Cost to remove structure on land $10,000
Paving of parking lot 10,000
Proceeds from sale of metal from demolished structure 3,000
Foundation work 15,000
Landscaping costs 12,000
Parking lot lighting 10,000
Direct materials - Warehouse 105,000
Electrical/Plumbing contractors 25,000
Closing costs on land purchase 5,000
Hourly wage rate - Workers 25
Question 1: What is the amount in the Land account related to this construction project?