What is new estimate of engineering costs

Assignment Help Project Management
Reference no: EM132009572

You have just been assigned as Project Manager (PM) to the Kuraiz-Reconda Fiber Optic Cable (KRFOC) project. You are preparing your cost estimate for the project and your Project Engineer (PE) tells you it will take 300 hours to complete the design effort. Your Finance Manager (FM) tells you that engineering labor is $100 an hour. Fortunately for you, unfortunately for them, you are a graduate, specializing in project management in general and advanced project management techniques.

Upon questioning, your PE admits that the 300 hours is just a guess, that under the best circumstances, meaning you quit bugging him with inane questions, it may take only 250 hours. However, it could take as long as 500 hours (if you do not leave him alone to do his job). He stands by his estimate that it will normally take 300 hours. Hint: this is a triangular distribution.

Thinking back to your school days, you wonder if all engineers cost $100 per hour. Upon questioning, your FM admits that this is an average cost, that some are higher, some are lower. You direct him to give you the distribution of all engineer labor rates. With a lot of help (your FM does not have the benefit of your education), he replies that the labor rate is normally distributed with a mean of $100 and a standard deviation (he is still not sure what that is) of $25.

Please answer the following two questions:

  1. Using this information and a wonderful tool you mastered, Crystal Ball (CB), what is the mean cost of your engineering effort?
  2. You are about to present your cost estimate to your sponsor when you remember that he was once a Professor. You recall, too, that he wore both a belt and suspenders and you suspect that this meant he might be a bit conservative. You therefore decide to provide an engineering cost estimate such that you are confident that 90% of the time your actual costs would be less than that value and that no more than 10% of the time would you exceed that value. What is your new estimate of engineering costs?

Be sure to provide the results of your CB simulation.

Reference no: EM132009572

Questions Cloud

Ace hardware is considering purchasing smaller chain : Ace hardware is considering purchasing a smaller chain, Brown hardware. What is the value of Browns to Ace?
Discuss these inter-governmental relations : Discuss these inter-governmental relations and note the importance of the increasing use of technology to improve efficiency.
Expectations theory-what is current two-year rate : According to the expectations theory, what is the current two-year rate?
What are some ethical considerations in change management : What are some ethical considerations in change management? How does cost of a change impact the ethical aspect of a change request?
What is new estimate of engineering costs : You therefore decide to provide an engineering cost estimate such that you are confident that 90% of the time your actual costs would be less than
Is social media actually making us less social : How does digital technology and social networks affect our social and interpersonal skills? Is social media actually making us less social?
Prepare entry c for consolidation : On January 1, 2013, Telconnect acquires 70 percent of Bandmor for $490,000 cash. If Telconnect has applied the partial equity method, prepare Entry C for 2015
Compute the value of this stock price in five years : Compute the value of this stock price in five years Calculate the present value of these cash flows using an 11 percent discount rate.
What states are doing to encourage growth : Find the report "Making" Our Future: What States Are Doing to Encourage Growth in Manufacturing through Innovation, Entrepreneurship, and Investment".

Reviews

Write a Review

Project Management Questions & Answers

  Create a project schedule and align resources

Create a project schedule and align resources, Analyze project schedule and resource allocation

  Managerial roles and gap analysis

Write a report on Managerial Roles and Gap Analysis

  Questionaire on project management

Questionaire on Project Management

  Describe the market growth rate for product

Describe the market growth rate for product and service.

  Prepare a work plan and project schedule - gantt chart

Design an online system for the human resources department to manage available job positions.

  Project risk management approach

How does a project risk management approach pro-vide an early warning signal for impending problems or issues

  Black-scholes options pricing model

Calculate the payoff and the profits for investments

  Describe the features or characteristics of product

Describe the features or characteristics of your product or service.

  Write paper on inventory management system

Write paper on Inventory Management System.

  Analysis of the overall project risk

Analysis of the overall project risk

  Investment and performance analysis

Evaluate the usefulness of ROCE

  Distribution strategy and project management

Distribution strategy and project management

Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd