A project consists of nine major activities, as shown below. There are three separate paths in the network: a-c-f, b-d-g, and e-h-i.
(A) What is expected project duration time?
(B) Determine the probability that the project will take more than 35 weeks to complete. (All times are in weeks.)
Activity: a, b, c, d, e, f, g, h, I
Exp Duration: 7, 10, 9, 11, 16, 14, 10, 8, 8
Std. Dev.: 1, 1, 2, 2, 2, 2, 2, 1, 2
I need to map out the path and determine the critical path before estimating percentages.