The following represents a project that should be scheduled using CPM:
Activity Immediate Predecessors Times(days)
a m b
A - 1 3 5
B - 1 2 3
C A 1 2 3
D A 2 3 4
E B 3 4 11
F C,D 3 4 5
G D,E 1 4 6
H F,G 2 4 5
a. Draw the network.
b. What is the critical path?
c. What is the expected project completion time?
d. What is the probability of completing this project within 16 days?
Complete a three period MOVING AVERAGE Forecast for periods 4 through 11. Complete a WEIGHTED MOVING AVERAGE Forecast for periods 4 - 11 using the weights assigned to your data set
Determine the fraction defective in each sample. If the true fraction of defective for this process is unknown, what is your estimate of it?. What is your estimate of the mean and standard deviation of the sampling distribution of fractions defective..
A large bakery buys flour in 25-pound bags. The bakery uses an average of 4,800 bags a year. Preparing an order and receiving a shipment of flour involves a cost of $10 per order.
1. Discuss the functions of inventory for different organizations in the supply chain associated with two of four members from the following list - manufacturer, distributor, supplier, or retailer.2. Based on your personal knowledge, select a specifi..
The process is being planned to have a usage rate of fifty pieces per hour. Each container is designed to hold ten pieces. It takes an average of thirty minutes to complete a cycle. Explain how many containers will be needed.
What is moral integrity? How do the experts views of moral integrity differ? What temptations will you face in choosing moral integrity for your professional actions? As a healthcare administrator, what will be the best way to maintain your moral int..
Explain the concept of structural holes and it affects value creation and value extraction. Based on this discussion, determine some of the skills essential to be a successful general manager.
What is a job analysis (e.g., what data is gathered, who is involved, what methods are available, etc.) and the uses of job analysis data?
Elucidate how does Henry Larsen get away with such egregious behaviour in the Orion Shield case. Processes to consider may be related to policies also procedures, human resource management also customer service.
Assume that the objective function coefficient for X changes from 8 to 6. Does the optimal solution change? Use the graphical solution procedure to find the new optimal solution.
A car rental agency uses 96 boxes of staples a year. The boxes cost $4 each. It costs $10 to order staples, and carrying costs are $0.80 per box on an annual basis
Assume that you are part of a mediation team that has been brought in to help overcome an impasse between negotiators who are deliberating the use of embryonic stem cells for a research project. The decision makers are polarized along ethical and rel..
Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!
whatsapp: +1-415-670-9521
Phone: +1-415-670-9521
Email: [email protected]
All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd