1. What is a common term for "life cycle analysis?
a. Material and Labor take-off
b. Construction cost analysis
c. Cradle-to-grave analysis
d. Economic analysis
2. The typical team members of in creating a building are which one of the following?
a. Construction manager, design, contractor
b. Owner, designer, contractor
c. Owner, engineer, construction manager
d. Owner, design/ builder
3. All of the following are occupancy types, except?
a. H-S
b. V-B
c. R-1
d. M
4. The owner contracts with just one entity for which of the following delivery methods?
a. Design/ build
b. Design/bid/build
c. Fixed-fee
d. Cost-plus
5. What type of bonds are performance and payment bonds
a. Incentive bonds
b. lump sum bonds
c. Surety bonds
6. What is the term used to describe the least time for completion of a project?
a. Construction sequence
b. Phased construction
c. Critical path
d. Gantt charting