What impact would this have on the critical path

Assignment Help Operation Management
Reference no: EM131357122

Four Squares Productions, a firm hired to coordinate the release of the movie Pirates of the Caribbean: On Stranger Tides (starring Johnny Depp), identified 16 activities to be completed before the release of the film.

a) How many weeks in advance of the film release should Four Squares have started its marketing campaign? What is the critical path? The tasks (in time units of weeks) are as follows:

ACTIVITY

IMMEDIATE PREDECESSORS

OPTIMISTIC TIME

MOST LIKELY TIME

PESSIMISTIC TIME

A

-

1

2

4

B

-

3

3.5

4

C

-

10

12

13

D

-

4

5

7

E

-

2

4

5

F

A

6

7

8

G

B

2

4

5.5

H

C

5

7.7

9

I

C

9.9

10

12

J

C

2

4

5

K

D

2

4

6

L

E

2

4

6

M

F, G, H

5

6 6

5

N

J, K, L

1

1.1

2

O

I, M

5

7

8

P

N

5

7

9

b) If activities I and J were not necessary, what impact would this have on the critical path and the number of weeks needed to complete the marketing campaign?

Reference no: EM131357122

Questions Cloud

Write a personal reflection on why you chose the topic : Identify the three reasons why this category and topic are meaningful to you - Each main body paragraph should match the reasons stated in your thesis. Suggested paragraph length is 5-7 sentences each.
What is an application service provider (asp) : What are reasons for using external and internal sources of hardware?
Read the essay and comments and fix the essay : Given the link of an video. "Murder on a Sunday Morning on youtube.", Read the essay and comments. and fix the essay.
What are the external sources of software : What are reasons for developing software internally versus acquiring it from external sources?
What impact would this have on the critical path : If activities I and J were not necessary, what impact would this have on the critical path and the number of weeks needed to complete the marketing campaign
What is the role of survey in a real estate transaction : Research surveys and answer these questions in a memo to your attorney:What is a survey?What is the role of survey in a real estate transaction?Explain each of these methods for describing real property:Government Rectangular System.
What are the specific goals of this systems survey : Indicate specific quantifiable benefits and costs that should be examined in assessing the economic feasibility of any solutions that might be proposed. Explain how you would go about quantifying each benefit or cost.
Prepare a deed from albert wilson who is single to robert : Robert Brown and Alice Brown, his wife, are entering into a contract to purchase the property. The sale price is $200,000. The Browns will tender $10,000 as down payment upon signing (earnest money) and pay an additional $10,000 within 20 days of ..
What is latitude longitude coordinate for favorite landmark : Using Google Earth, find your house/apartment building or favorite landmark in your neighborhood. What is latitude/longitude coordinate for this "favorite landmark"?

Reviews

Write a Review

Operation Management Questions & Answers

  Book review - the goal

Operations Management is about a book review. Title of the book is "Goal". This book has been written by Dr. Eliyahu Goldartt. The book has been appreciated by many as one of those books which offers an insight into the operations and strategic capac..

  Operational plan in hospitality enterprise

Operational plan pertaining to a hospitality enterprise is given in detail in the solution. The operational plan is an important plan or preparation which gives guidelines regarding the role and responsibilities of each and every operation at all lev..

  Managing operations and information

Recognise the importance of a strategic approach to the development and deployment of organisational information systems. Demonstrate an understanding of the importance of databases and their integration to the organisation's overall information mana..

  A make-or-buy analysis

An analysis of the holding costs, including the appropriate annual holding cost rate.

  Evolution and contributor of operations management

Briefly explain Evolution and contributor of Operations management.

  Functions and responsibilities of an operations manager

A number of drivers of change have transformed the roles, functions and responsibilities of an operations manager over recent years. These drivers have not only been based on technological innovations but also on the need for organisations to develop..

  Compute the optimal order quantity

Compute the Optimal Order quantity of DVD players. Determine the appropriate reorder point.

  Relationship to operations practice in the organisation

Evaluate problems in operations and identify approaches to overcoming them. Critically evaluate operating plans and identify areas for improvement. Justify, implement and evaluate changes to operations in line with modern approaches.

  A make or buy analysis

Develop a report for Figi Fabricating that will address the question of whether the company should continue to purchase the part from the supplier or begin to produce the part itself.

  Prepare a staffing plan

Prepare a staffing plan showing the change of your unit from medical/surgical staffing to oncology staffing.

  Leadership styles in different organizations

Ccompare the effectiveness of different leadership styles in different organizations

  Risk management tools and models

Be able to understand the concept of risk, roles and responsibilities for risk management and risk management tools and models.

Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd