What component of the project plan will help you

Assignment Help Operation Management
Reference no: EM13248462

You are the project manager of a project that has already been initiated and has been in progress for two months. The project plan was completed several weeks prior to its actual initiation. The customer recently met with the sponsor regarding some new requirements.

During the weekly status meeting, the sponsor communicates to you that the new requirements are critical to the success of your company and should be immediately added to the project. You become concerned that the project cost and schedule will get out of hand due to the new requirements.

Based on the scenario, answer the following questions:
Should you add the new requirements from the sponsor to the plan? Explain why or why not.

What component of the project plan will help you determine how to manage this request for new requirements? Explain how this component is used to manage project changes.

Explain the steps that you would take to manage the situation to ensure that the project is on track.

 

Reference no: EM13248462

Questions Cloud

Explain what percent of ammonia dissociates to the elements : A 20L vessel is filled with 1.00 mol of ammonia. NH3. What percent of ammonia dissociates to the elements if equilibrium is reached at 345C
Explain the concepts of the product life cycle : Explain the concepts of the product life cycle and identify the four phases of the product development cycle. Make sure you define the strategies used in each phase.
Define positive direction in the forward direction : You drive your 1,345-kg car at a constant speed of 23 mph a distance of 71 m down a ramp that has a grade of 14 %. Define positive direction in the forward direction
Determine the sum or difference of two numbers : Use the simulation timing diagram to compare the worse case time to do an operation with your ALU with the worst case using the 74LS381. State which operation takes the longest and list the time required for both ALU's.
What component of the project plan will help you : What component of the project plan will help you determine how to manage this request for new requirements? Explain how this component is used to manage project changes.
Determine the second ball after the collision : A 4.4kg ball with a velocity of 5.0m/s in the+x-direction collides head-on elastically with a stationary 2.5kg ball. What is the speed of the second ball after the collision
Determine the stability of the closed-loop system : The loop transfer function L(S) of a single-feedback-loop control system is given below. Sketch the Nyquist plot of L(jw) for w=0 to w=infinity, Determine the stability of the closed-loop system.
How much fuel is required to spin up the asteroid : Consider Iron asteroid (density 7900 kg/m^3) shaped like a cylinder 5.0 km long and 3.0 km in diameter, How much fuel is required to spin up the asteroid
Describe its competitive advantage using the resource-based : Pick a publicly traded company. Describe its competitive advantage using the resource-based model of above average returns.

Reviews

Write a Review

Operation Management Questions & Answers

  Book review - the goal

Operations Management is about a book review. Title of the book is "Goal". This book has been written by Dr. Eliyahu Goldartt. The book has been appreciated by many as one of those books which offers an insight into the operations and strategic capac..

  Operational plan in hospitality enterprise

Operational plan pertaining to a hospitality enterprise is given in detail in the solution. The operational plan is an important plan or preparation which gives guidelines regarding the role and responsibilities of each and every operation at all lev..

  Managing operations and information

Recognise the importance of a strategic approach to the development and deployment of organisational information systems. Demonstrate an understanding of the importance of databases and their integration to the organisation's overall information mana..

  A make-or-buy analysis

An analysis of the holding costs, including the appropriate annual holding cost rate.

  Evolution and contributor of operations management

Briefly explain Evolution and contributor of Operations management.

  Functions and responsibilities of an operations manager

A number of drivers of change have transformed the roles, functions and responsibilities of an operations manager over recent years. These drivers have not only been based on technological innovations but also on the need for organisations to develop..

  Compute the optimal order quantity

Compute the Optimal Order quantity of DVD players. Determine the appropriate reorder point.

  Relationship to operations practice in the organisation

Evaluate problems in operations and identify approaches to overcoming them. Critically evaluate operating plans and identify areas for improvement. Justify, implement and evaluate changes to operations in line with modern approaches.

  A make or buy analysis

Develop a report for Figi Fabricating that will address the question of whether the company should continue to purchase the part from the supplier or begin to produce the part itself.

  Prepare a staffing plan

Prepare a staffing plan showing the change of your unit from medical/surgical staffing to oncology staffing.

  Leadership styles in different organizations

Ccompare the effectiveness of different leadership styles in different organizations

  Risk management tools and models

Be able to understand the concept of risk, roles and responsibilities for risk management and risk management tools and models.

Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd