Question: In an NEC Option B Contract, a contractor has used imported fill to fill in a drainage run. The supervisor is concerned there are signs of settlement in a section of this drainage run. This scenario occurs 6 months before completion. a. What should the supervisor do as soon as he sees this issue?
b. The contractor feels that the settlement is very minor and in a rarely trafficked area of the site. He is worried as excavating the area will cause major disruption to installation of an incoming gas supply - this has been programmed with an external gas supplier and has taken many weeks to negotiate. If the contractor misses the slot with the gas supplier, he may have to wait weeks for another date and there will be a knock-on delay to the programme. In this scenario, what can he suggest happens?
c. Having considered the contractor's proposal, the PM and Supervisor want to investigate the settlement further. What clause of the contract does he use to ask the contractor to look at this problem? What information does he need to give the contractor?
Speculate the outsourcing and offshoring opportunities. Details regarding the type of business activities that the company is involved in.
SRM752 Advanced Project Management - Deakin University - Project management PLAN - Show briefly how scope, risk, communication and procurement will be managed
What style of training is best for one and one training and apprenticeships withing construction?
Determine what is known and what is unknown about the project. Explain why this might be important to the project - You have a 10 day window from the time the new building is complete to the time you must be out of the old building.
Project Constraints - Analyzing possible project constraints and how to manage them. Identifying (with rationale) whether the project is time-constrained, resource-constrained (or both) , and how to manage the situation
What is the advantages and disadvantages, from the owner's perspective, of bidding to a sole source contractor. Also, discuss when sole sourcing may be warranted or justified.
Deerborn Electronics Scenario: You work for Deerborn Electronics, a multinational firm providing parts for mobile devices.
How has the passage and enactment of numerous federal and state laws affected the employment selection process?
Assessment activities can be completed either in real workplace environment or in a simulated environment such as your classroom
explain the role of stakeholders in implementing a quality management process. Please be sure you are discussing the stakeholder in terms of implementing a quality management process.
What benefits can a project manager gain from networking? Explain at least six. Identify your own reason(s) for networking over the next 2 years.
Why did UW decide to adopt a committee structure to administer its ERM program instead of designating a senior level Chief Risk Officer?
Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!
whatsapp: +1-415-670-9521
Phone: +1-415-670-9521
Email: [email protected]
All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd