What are various tools for stakeholder engagement control

Assignment Help Operation Management
Reference no: EM132236178

Case Study The City of Mayflower Community Center Construction Project John Williams was hired by the city of Mayflower on June 8, 2014, as a building inspector. One of his assignments was to inspect city community center on August 1, 2014. During the city planning commission meeting in the city hall on August 15, 2014, Raul Chavez, the project manager for the city community center construction project, discovered that the inspection of the city community center was not completed by inspector John on August 1, 2014, as planned. Raul was concerned because several other city projects depended on successful completion of the construction of the city community center. With the community center project schedule slipping, all other dependent projects would be delayed. Upon further investigation, Raul found that inspector John did not approve the project because he found project documentation incorrect and incomplete, and he had sent the project detailed instructions on how to prepare and submit the project documents for approval. Raul invited his project core team members, the general contractor, city manager, site manager, and few other key stakeholders for an urgent meeting to determine the potential impact of the delay. Further, he facilitated a brainstorm session to understand plan B and potential corrective actions to mitigate the risk of schedule delays. The team collectively came up with the following impacts: • Impact to scope: Plan B or alternative solutions may add additional unplanned work to the scope. • Impact to schedule: If the city community center inspection is not approved latest by August 29, 2014, the dependent projects will jump to critical path involving day-by-day schedule slip. • Impact to cost: If resources are asked to work overtime to speed up the completion of the required project document, it will cause cost overrun. Raul decided to consult experts to seek their judgment. He consulted with Tim Allen who had just completed a similar project successfully to mitigate the risk of failing the inspection the second time. Tim helped the project team to develop a workable plan to gather, organize, and present the information per building inspector’s requirements. The project team led by project manager Raul acted upon Tim’s advice. Result: The Mayflower city community center inspection was approved on August 23, 2014. Case Study Questions 1. Who are the stakeholders in this case and who is controlling the stakeholder engagement? 2. Which project constraints have been included in this case for impact assessment? Describe the impact. 3. What are various tools for stakeholder engagement control discussed in this chapter? Which tool was used by Raul in this case? 4. What are the lessons learned from this case?

Reference no: EM132236178

Questions Cloud

Breach of contract for the sale of electronic parts : On January 15, 2018, Anders brought an action against Barnes for breach of a contract for the sale of electronic parts.
Should stringtown focus on job fit or organization fit : Which of the overall HR strategies would be best for Stringtown Iron Works? Should Stringtown focus on job fit or organization fit?
According to the strategic sourcing matrix : According to the strategic sourcing matrix, complexity of the market focus on:
Conventions for the upcoming year on your schedule : How you would use satisfied customers to prospect for meetings and conventions for the upcoming year on your schedule.
What are various tools for stakeholder engagement control : What are various tools for stakeholder engagement control discussed in this chapter? What are the lessons learned from this case?
Discuss the concept of project management family : Discuss the concept of “project management family” within the context of this case. What did Comau do to control project communications?
Electricity to both residential and commercial consumers : Solenoid has been the nation’s leading distributor of electricity to both residential and commercial consumers.
Managed-conflict views of conflict while providing examples : Differentiate among the traditional, interactionist, and managed-conflict views of conflict while providing examples.
Valid reasons for scheduling resources : What is true of risks associated with leveling resources? Which of the following are valid reasons for scheduling resources?

Reviews

Write a Review

Operation Management Questions & Answers

  Book review - the goal

Operations Management is about a book review. Title of the book is "Goal". This book has been written by Dr. Eliyahu Goldartt. The book has been appreciated by many as one of those books which offers an insight into the operations and strategic capac..

  Operational plan in hospitality enterprise

Operational plan pertaining to a hospitality enterprise is given in detail in the solution. The operational plan is an important plan or preparation which gives guidelines regarding the role and responsibilities of each and every operation at all lev..

  Managing operations and information

Recognise the importance of a strategic approach to the development and deployment of organisational information systems. Demonstrate an understanding of the importance of databases and their integration to the organisation's overall information mana..

  A make-or-buy analysis

An analysis of the holding costs, including the appropriate annual holding cost rate.

  Evolution and contributor of operations management

Briefly explain Evolution and contributor of Operations management.

  Functions and responsibilities of an operations manager

A number of drivers of change have transformed the roles, functions and responsibilities of an operations manager over recent years. These drivers have not only been based on technological innovations but also on the need for organisations to develop..

  Compute the optimal order quantity

Compute the Optimal Order quantity of DVD players. Determine the appropriate reorder point.

  Relationship to operations practice in the organisation

Evaluate problems in operations and identify approaches to overcoming them. Critically evaluate operating plans and identify areas for improvement. Justify, implement and evaluate changes to operations in line with modern approaches.

  A make or buy analysis

Develop a report for Figi Fabricating that will address the question of whether the company should continue to purchase the part from the supplier or begin to produce the part itself.

  Prepare a staffing plan

Prepare a staffing plan showing the change of your unit from medical/surgical staffing to oncology staffing.

  Leadership styles in different organizations

Ccompare the effectiveness of different leadership styles in different organizations

  Risk management tools and models

Be able to understand the concept of risk, roles and responsibilities for risk management and risk management tools and models.

Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd