What are the spending and schedule variances for the project

Assignment Help Applied Statistics
Reference no: EM132492344

PMAN635 Quantitative Methods in Project Management - University of Maryland Global Campus

Problem 1.A project in its 26th week has an actual cost of $250,000. It was scheduled to have completed $325,000 worth of work at that point in the project. For the work performed to date, the budgeted value is $300,000.  The project has a total budget of $1,500,000.  What are the cost and schedule variances for the project? What are the SPI and CPI?  Assuming that both schedule and cost variances will affect the remaining work, what is the EAC?

a.       CV =

b.      SV =

c.       SPI =

d.      CPI =

e.      EAC =

Problem 2. A project has just completed its 87thtask of a total of 150 tasks in its project plan. The project has a total budget of $1,500,000.  It was scheduled to have spent $500,000 at this point in the plan, but has actually spent only $400,000. The project manager estimates that the value of the work actually finished is $300,000.  

What are the spending and schedule variances for the project? What are the SPI and CPI?  What is the EAC, assuming the remaining work will be completed as budgeted?  Is this likely?

a.       CV =

b.      SV =

c.       SPI =

d.      CPI =

e.      EAC =

Problem 3. The following project is at the end of its 6th week. Find the cost and schedule variances. Also find the CPI and SPI. Then find the critical ratio of the project using earned value calculations. Finally, calculate the EAC for the project by at least two different methods.

Activity

Predecessor

Duration (wks)

Budget  at Completion    ($)

Actual Cost ($)

%Complete

a

-

2

300

400

100

b

a

3

200

250

100

c

b

3

300

300

100

d

b

5

600

200

30

e

c,d

4

400

-

0

a.       CV =

b.      SV =

c.       CPI =

d.      SPI=

e.      CR=

f.        EAC=

Problem 4. Answer the questions for the following case:

Stoneworth Paving Company specializes in highway paving jobs for state of Virginia. When the State first awarded Stoneworth the contract, they stipulated a 1% penalty for each week Stoneworth was late on a completion date. Preston Flintrock, the project coordinator for Stoneworth, began to notice that the last two jobs were three weeks late, and the paving job that was due to be completed in the next two weeks was behind schedule. When Preston went in the field to investigate, he found the job to be understaffed, supplier delays, and a high work rejection/repaving needed. As a result, Preston decided to establish a better system of project control and present it to the boss.

a. If you were Preston, what characteristics would you look for in a new control system? Explain.

b. Will a new control system be adequate for the problem? Explain.

Reference no: EM132492344

Questions Cloud

Complete the perpetual system and fifo method : Complete the following using the Perpetual System And the FIFO method. I have started it with the beginning inventory of 10 units at $10
Understand the role of the federal reserve : How much discretion should the Fed have? Should the Fed try to fine-tune the economy or simply keep money supply growing at a steady pace?
Discuss about appropriate creative arts classroom spaces : Write a 500-750-word essay using research about appropriate creative arts classroom spaces. Explain your rationale for both spaces that you designed.
Prepare a record the correct letter increase to bank balance : Prepare a record the correct letter increase to bank balance, decrease to bank balance,increase to company cash balance, decrease to company cash balance
What are the spending and schedule variances for the project : What are the spending and schedule variances for the project? What are the SPI and CPI? What is the EAC, assuming the remaining work will be completed as budge
What value difference add to your educational experience : After learning more about what GCU is all about by reading the GCU Doctrinal Statement and Christian Identity and Heritage, how do you think GCU's Christian.
What would tell the investors about investing in the stock : Assuming CAPM is correct, what should be the price of the stock? what would you tell the investors about investing in the stock?
Will a new control system be adequate for the problem : What characteristics would you look for in a new control system and Will a new control system be adequate for the problem? Explain
Break even for the increase in machine expenses : What is the minimum change in dollar sales needed to break even for the increase in machine expenses?

Reviews

len2492344

4/14/2020 3:28:32 AM

please read the entire assignment and answer all questions and please show calculation to all solution in excel doc and word.doc

Write a Review

Applied Statistics Questions & Answers

  Hypothesis testing

What assumptions about the number of pedestrians passing the location in an hour are necessary for your hypothesis test to be valid?

  Calculate the maximum reduction in the standard deviation

Calculate the maximum reduction in the standard deviation

  Calculate the expected value, variance, and standard deviati

Calculate the expected value, variance, and standard deviation of the total income

  Determine the impact of social media use on student learning

Research paper examines determine the impact of social media use on student learning.

  Unemployment survey

Find a statistics study on Unemployment and explain the five-step process of the study.

  Statistical studies

Locate the original poll, summarize the poling procedure (background on how information was gathered), the sample surveyed.

  Evaluate the expected value of the total number of sales

Evaluate the expected value of the total number of sales

  Statistic project

Identify sample, population, sampling frame (if applicable), and response rate (if applicable). Describe sampling technique (if applicable) or experimental design

  Simple data analysis and comparison

Write a report on simple data analysis and comparison.

  Analyze the processed data in statistical survey

Analyze the processed data in Statistical survey.

  What is the probability

Find the probability of given case.

  Frequency distribution

Accepting Manipulation or Manipulating

Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd