What are the savings with the new schedule

Assignment Help Project Management
Reference no: EM131276429

Assignment

Analytics Exercise: An MRP Explosion-Brunswick Motors Recently, Phil Harris, the production control manager at Brunswick, read an article on time-phased requirements planning. He was curious about how this technique might work in scheduling Brunswick's engine assembly operations and decided to prepare an example to illustrate the use of time-phased requirements planning. Phil's first step was to prepare a master schedule for one of the engine types produced by Brunswick: the Model 1000 engine. This schedule indicates the number of units of the Model 1000 engine to be assembled each Part during the last 12 Parts and is shown below. Next, Phil decided to simplify his requirements planning example by considering only two of the many components that are needed to complete the assembly of the Model 1000 engine. These two components, the gear box and the input shaft, are shown in the product structure diagram below. Phil noted that the gear box is assembled by the Subassembly Department and subsequently is sent to the main engine assembly line. The input shaft is one of several component parts manufactured by Brunswick that are needed to produce a gear box sub assembly. Thus, levels 0, 1, and 2 are included in the product structure diagram to indicate the three manufacturing stages that are involved in producing an engine: the Engine Assembly Department, the Subassembly Department, and the Machine Shop. The manufacturing lead times required to produce the gear box and input shaft components are also indicated in the product structure diagram. Note that two Parts are required to produce a batch of gear boxes and that all the gear boxes must be delivered to the assembly line parts stockroom before Monday morning of the Part in which they are to be used. Likewise, it takes three Parts to produce a lot of input shafts, and all the shafts that are needed for the production of gear boxes in a given Part must be delivered to the Sub Assembly Department stockroom before Monday morning of that Part. In preparing the MRP example Phil planned to use the worksheets shown on the next page and to make the following assumptions:

1. Seventeen gear boxes are on hand at the beginning of Part 1, and five gear boxes are currently on order to be delivered at the start of Part 2.

2. Forty input shafts are on hand at the start of Part 1, and 22 are scheduled for delivery at the beginning of Part 2.
Questions:

1.) Initially, assume that Phil wants to minimize his inventory requirements. Assume that each order will be only for what is required for a single period. Using the following forms, calculate the net requirements and planned order releases for the gear boxes and input shafts. Assume that lot sizing is done using lot-for- lot (L4L).

2.) Phil would like to consider the costs that his accountants are currently using for inventory carrying and setup for the gear boxes and input shafts. These costs are as follows:

Part Cost

Gear Box Setup 5 $90/order
Inventory carrying cost 5 $2/unit/Part
Input Shaft Setup 5 $45/order
Inventory carrying cost 5 $1/unit/Part
Model 1000 master schedule
Part 1 2 3 4 5 6 7 8 9 10 11 12
Demand 15 5 7 10 15 20 10 8 2 16
Model 1000 product structure
Engine assembly
Gear box
Crankcase Lead time = 2 Parts
Used: 1 per engine
Input shaft
Lead time = 3 Parts
Used: 2 per gear box

Given the cost structure, evaluate the cost of the schedule from question 1. Assume inventory is valued at the end of each Part.

3.) Find a better schedule by reducing the number of orders and carrying some inventory. What are the savings with this new schedule?
Engine assembly master schedule

Part 1 2 3 4 5 6 7 8 9 10 11 12
Quantity
Gear box requirements
Part 1 2 3 4 5 6 7 8 9 10 11 12
Gross requirements
Scheduled receipts
Projected available balance
Net requirements
Planned order release
Input shaft requirements
Part 1 2 3 4 5 6 7 8 9 10 11 12
Gross requirements
Scheduled receipts
Projected available balance
Net requirements
Planned order release
This is what I have so far, not sure if it's correct:
Gear box requirements
Part 1 2 3 4 5 6 7 8 9 10 11 12
Gross requirements 15 5 7 10 15 20 10 8 2 16
Scheduled receipts 5 5 10 15 20 10 8 2 16
Projected available balance 2 2
Net requirements 5 10 15 20 10 8 2 16
Planned order release 5 10 15 20 10 8 2 16
Input shaft requirements
Part 1 2 3 4 5 6 7 8 9 10 11 12
Gross requirements 10 20 30 40 20 16 4 32
Scheduled receipts 22 38 20 16 4 32
Projected available balance 30 32 32 2
Net requirements 38 20 16 4 32
Planned order release 38 20 16 4 32

Reference no: EM131276429

Questions Cloud

What is groupthink : What is Groupthink? Explain this phenomenon using research on conformity, obedience, and group polarization (explain what these are and how they are different from one another).
How has wireless technology change your quality of your work : How has wireless technology changed your quality of life or your work environment? How are wireless technologies used by organizations to form a communication channel with clients?
Investing on r&d and marketing : Adidas and Nike both appear to be Marris type players and are investing more on R&D and marketing - Each one is constantly releasing new innovations with Adidas defending it is position as the leader in the soccer market segment.
Business law perspective what a budding entrepreneur : Explains from a business law perspective what a budding entrepreneur should know in order to successfully establish a domestic trading business in children’s garments where international contracts are entered into to: Once purchased the fabric is shi..
What are the savings with the new schedule : Find a better schedule by reducing the number of orders and carrying some inventory. What are the savings with this new schedule?
Determine the flow work of the helium in the supply : Now the valve is opened, and helium is allowed to flow into the tank until the pressure reaches 200 kPa, at which point the valve is closed. Determine the flow work of the helium in the supply line and the final temperature of the helium in the ta..
The affordable care act : The Affordable Care Act brought about many things which have helped patients. For example, elimination of the pre-existing condition clause has enabled many patients to get health insurance who otherwise would have had no options. The most controvers..
Are the signs of friendship the same everywhere : What is Yuri's view of Americans, and on what does he base this perception?Are the signs of friendship the same everywhere?
Clinical quality value analysis : Clinical Quality Value Analysis. You identified leadership engagement and communicating a clear case for change as critical success factors. I would strongly agree. I wonder, however, how much time leaders should spend on making the case for change.

Reviews

Write a Review

Project Management Questions & Answers

  Create a project schedule and align resources

Create a project schedule and align resources, Analyze project schedule and resource allocation

  Managerial roles and gap analysis

Write a report on Managerial Roles and Gap Analysis

  Questionaire on project management

Questionaire on Project Management

  Describe the market growth rate for product

Describe the market growth rate for product and service.

  Prepare a work plan and project schedule - gantt chart

Design an online system for the human resources department to manage available job positions.

  Project risk management approach

How does a project risk management approach pro-vide an early warning signal for impending problems or issues

  Black-scholes options pricing model

Calculate the payoff and the profits for investments

  Describe the features or characteristics of product

Describe the features or characteristics of your product or service.

  Write paper on inventory management system

Write paper on Inventory Management System.

  Analysis of the overall project risk

Analysis of the overall project risk

  Investment and performance analysis

Evaluate the usefulness of ROCE

  Distribution strategy and project management

Distribution strategy and project management

Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd