What are the quantities of planned order releases

Assignment Help Operation Management
Reference no: EM13225903

Question 1

Which one of the following statements about lot-sizing rules is TRUE?

The periodic order quantity (POQ) rule seeks to create inventory remnants.

If the POQ rule is used, an item's lot size can vary each time an order is placed.

The lot-for-lot (L4L) rule is a special case of the fixed-order quantity (FOQ) rule.

All lot-sizing rules seek to minimize inventory levels.

Question 2

MRP explosion means estimating the total number of:

subassemblies, components, and raw materials needed for each parent item.

raw materials to be purchased from all suppliers.

parts to be produced for each parent item.

parts needed to be produced less the number of parts on hand for each parent item.

Question 3

Which one of the following is a feature of MRP II, but not available in basic MRP systems?

Financial reporting

Action notices

Dispatch lists

Capacity reporting

Question 4

The Big Mistake Company uses an MRP system. However, the company's database contains many inaccuracies. Which type of inaccuracy is most likely to result in incorrect planned order release quantities for its dependent demand items?

Incorrect routings

Incorrect bills of materials

Incorrect cost and pricing data

Incorrect machine capacity data

Question 5

Which of the following statements on MRP is TRUE?

The payoffs from MRP tend to be greater when there are more BOM levels and larger lot sizes.

When MRP systems are enhanced to include financial reporting, they are called basic MRP systems, or "little mrps."

The fixed-order quantity (FOQ) eliminates remnants.

MRP is an inventory control system that derives the gross requirements of the end items from purchase commitments with vendors.

Question 6

Use the following MRP record to answer the question.

1081_What will be the projected on-hand inventory quantity.png

What are the quantities of planned order releases for item XYZ for the first six weeks (weeks 1, 2, 3, 4, 5, and 6)?

35, 0, 0, 60, 0, 0

35, 0, 60, 0, 0, 0

5, 30, 0, 40, 20, 0

35, 0, 0, 40, 20, 0

Question 7

Table

2254_What will be the projected on-hand inventory quantity1.png

Use the information in Table. In which week will the second planned order release occur?

Week 1

Week 2

Week 3

Week 4, 5, 6, 7, or 8

Question 8

Use the following MRP record to answer the question.

2170_What will be the projected on-hand inventory quantity2.png

What will be the projected on-hand inventory quantity in week 7

Fewer than or equal to 30 units

Greater than 30 units but fewer than or equal to 60 units

Greater than 60 units but fewer than or equal to 90 units

Greater than 90 units

Question 9

Use the following MRP record to answer the question.

2234_What will be the projected on-hand inventory quantity3.png


Which one of the following statements about item QRS is TRUE?

Two order releases are needed.

The first planned receipt occurs in week 1.

The second planned order release quantity is 90 units.

The total planned order release quantity (summing up all eight weeks) is 190 units.

Question 10

Table

Consider the following MPS, BOM, and inventory data. A blank MRP record is shown below.

986_What will be the projected on-hand inventory quantity4.png

Master Production Schedule: The following table shows the MPS start quantities.

129_What will be the projected on-hand inventory quantity5.png

Bill of Material

Selected Inventory Data

974_What will be the projected on-hand inventory quantity6.png

Use the information in Table. Which one of the following statements about item C is TRUE?

It has a planned receipt of 80 units in week 3.

Its second planned order release is for 200 units in week 3.

It has a planned receipt of 180 units in week 6.

Its first planned order release is for 130 units in week 1.

Question 11

1.

Consider the following MPS, BOM, and inventory data. A blank MRP record is shown below.

2260_What will be the projected on-hand inventory quantity7.png

Master Production Schedule: The following table shows the MPS start quantities.

610_What will be the projected on-hand inventory quantity8.png

Bill of Material

Selected Inventory Data

1169_What will be the projected on-hand inventory quantity9.png

Use the information in Table 15.2. Which one of the following statements about item F is TRUE?

The first planned order release is for 205 units in week 3.

There will be exactly one action notice, which calls for the delay of the scheduled receipt until week 2.

There will be exactly one action notice, which calls for the release of a new order.

Both 2 and 3 are correct.

Question 12

Table

136_MRP record.png

Use the information in Table. Which one of the statements concerning item RST is TRUE?

The first planned receipt occurs in week 5.

There is an action notice needed to expedite the schedule receipt by one week.

The planned receipt in week 7 is 80 units.

There are exactly two planned order releases needed.

Question 13

Use the following MRP record to answer the question.

1961_MRP record1.png
Which one of the statements concerning item LMN is TRUE?

There will be exactly two action notices needed.

The planned order release quantity in week 4 is 80 units.

The planned receipt quantity in week 6 is 30 units.

The projected on-hand inventory in week 8 is 70 units.

Question 14

Table

36_MRP record2.png

Use the information from Table. If an FOQ of 75 units is used, how many planned order releases are there for item XYZ?

Zero or one

Two or three

Four or five

More than five

Question 15

349_MRP record3.png

Use the information from Table. If a POQ lot-sizing rule is used, where P = 3, how many planned order releases are there for item XYZ?

Zero or one

Two or three

Four or five

More than five

Question 16

Management wishes to use a POQ lot-sizing rule for an item that experiences an average demand of 30 units per week. If the desired average lot size is 120 units, what should P be?

Zero or one weeks

Two or three weeks

Four or five weeks

More than five weeks

Question 17

Case Study

Sunshine Manufacture produces three products: X, Y, and Z. The production of these end items is controlled by an MRP system. Each end item X is assembled with two components of A and one component of B. Each end item of Y is assembled with two components of C and one component of A. End item Z is assembled from one unit of D and one unit of C; D is manufactured from one unit of A; and C is manufactured from one unit of B.

Use the information in Case Study. If level-by-level processing is used, what is a correct order for processing components A, B, C, and D?

2126_record.png

Question 18

Table

403_MRP record4.png

Viola Products produces one item with the following bill of materials

1059_MRP record5.png

A recent check of their inventory reveals the following quantities on hand.

Use Table to answer this question. How many additional units of D are needed to produce 20 end items?

Fewer than 75

More than 75 but fewer than 95

More than 95 but fewer than 115

More than 115

Question 19

Table

740_MRP record6.png

Viola Products produces one item with the following bill of materials

1620_MRP record7.png

A recent check of their inventory reveals the following quantities on hand.

Use Table to answer this question. How many additional units of H are needed to produce 20 end items?

Fewer than 250

More than 250 but fewer than 350

More than 350 but fewer than 450

More than 450

Question 20

Table

595_MRP record8.png

Viola Products produces one item with the following bill of materials

540_MRP record9.png

A recent check of their inventory reveals the following quantities on hand.

Use Table 15.5 to answer this question. How many additional units of G are needed to produce seven end items?

0

11

22

33

Question 21

Viola Products produces one item with the following bill of materials

1162_MRP record10.png


A recent check of their inventory reveals the following quantities on hand.

816_MRP record11.png

Use Table to answer this question. How many additional units of J are needed to produce seven end items?

25

36

47

58

Question 22

Which of the following is NOT used to derive an item's gross requirements?

The MPS for immediate parents that are end items

The planned order releases for parents below the MPS level

The MPS components that are not purchased items

Any other requirements not originating in the MPS, such as the demand for replacement parts

Question 23

A technique used for projecting time-phased capacity requirements for workstations is called:

capacity requirements planning.

time-adjusted output control.

input-output control.

work center planning.

Question 24

Which of the following uses of MRP in promoting a healthy environment is NOT used?

An MRP system can track waste in a bill of materials as a component of an item.

When the master production schedule is developed for a product, reports can be generated that project the quantity of waste.

When the master production schedule is developed for a product, reports can be generated that project the timing of waste.

The MRP system can be used to communicate directly with the International Organization for Standardization to file ISO 9000 documentation.

Question 25

In terms of resource planning, service goods must focus on maintaining:

dependent demand levels at a maximum.

capacity to serve customers.

off-line resources in order to serve customers.

independent demand resources at a maximum.

Question 26

An example of a dependent demand item in a service is a:

menu in a restaurant.

jukebox in a club.

operating suite at a hospital.

a pilot's checklist for an airline.

Question 27

The service analogy to the bill of materials in a manufacturing company is the:

bill of resources.

bill of services.

bill of sub-services.

bill of tender.

Reference no: EM13225903

Questions Cloud

Explain structure of the molecule with the molecular formula : Deduce the structure of the molecule with the molecular formula C3H6 with a C13 NMR delta peak value of 27.8
Explain two models of substrate or enzyme complex formation : What are the names and principle differences in the two models of substrate/enzyme complex formation?
Explain aqueous environments for the polar acidic acid : Use condensed structures to illustrate the 3 possible charged species and the one neurtral species that can exist in aqueous environments for the polar acidic acid of your choice. Indicate which conditions are present in each of the four drawings.
Explain the functions of the prosthetic group : Name and list the functions of the prosthetic group(s) associated with a) HDLs , b) interferons, c) viruses , and d)hemoglobin
What are the quantities of planned order releases : Which type of inaccuracy is most likely to result in incorrect planned order release quantities for its dependent demand items - What are the quantities of planned order releases for item XYZ for the first six weeks
Explain what percentage of the acid is not ionized : A weak acid (HA) has a pKa of 4.904. If a solution of this acid has a pH of 4.356, what percentage of the acid is NOT ionized
Compute the edge length of the unit cell : From this information and the atomic mass, calculate the edge length of the unit cell. Now assume that rubidium atoms are spheres. Each corner sphere of the unit cell touches the body centered sphere. Calculate the radius of a rubidium atom.
State p-methylbenzoic acid with n-bromosuccinimide : Draw the organic product(s) of the reaction of p-methylbenzoic acid with N-bromosuccinimide in CCl4
Find out the percentage of vitamin c : This solution was made up to the mark in a 200ml volumetric flask with water. It was found 10mls of this solution required an average titre of 6.50ml of 0.05M HCl for neutralisation.

Reviews

Write a Review

Operation Management Questions & Answers

  Identify key gaps in planning for the exit

Identify key gaps in planning for the exit. Provide recommendations on the exit strategy. Is the sale the right one? What steps ought to be taken to maximize the sales-price?

  Estimate total overtime production cost

The president of Hill Enterprises, Terri Hill, projects the firm's aggregate demand requirements over the next 8 months as follows,

  Discuss the cost containment measures

What are three cost-containment measures that were implemented through the collective bargaining process in 1985? Why were these considered milestones in curtailing health benefit costs to employees?

  Illustrate what leadership actions you would take to adapt

Illustrate what Leadership actions you would take to adapt your business should subsequent happen in first three years of operations.

  Differentiate between avoiding risk and accepting risk

Differentiate between avoiding a risk and accepting a risk. Indicate the implications to a travel agency.

  How would you address the issues sigma is facing

Are there any change management theories, training concepts or organizational development models we have read about or been presented that would be useful in this situation? If so, which ones and why?

  Explain priority list of the information

Form a group in which each member represents a different functional area of a firm. Provide a priority list of the information that could be generated from an MPS

  Generic pharmaceuticals industry

How does Teva compete in the generic pharmaceuticals industry? What is its competitive advantage. Evaluate Teva's resources. Which are its most valuable ones?

  Compute five and seven month moving average

Compute a five and seven month moving average for the last 5 months of historical data (months 8 thru 12)

  Define scalability

A key factor that affects technology decisions is scalability. Define scalability. Explain the difference between high scalability, infinite scalability, and low scalability.

  Discuss about noted organization theorist

Discuss about noted organization theorist. Pressure for change originates in the environment; pressure for stability originates within the organization.

  Atorade and found out that the average weight was

Pepsi uses six-sigma technique to evaluate whether its 15 oz Gatorade has consistent weight. Pepsi took a sampling of 1000 15 oz Gatorade and found out that the average weight was 15.12 oz with a standard deviation of 0.3 oz. Pepsi considers a to..

Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd