10) Bragg's Bakery is building a new automated bakery in downtown Omaha. Here are the activities that need to be completed to get the new bakery build and the equipment installed.
Activity
Predecessor
Normal Completion Time (Weeks)
Crash Completion Time (Weeks)
Crash (Expediting) Cost/Week
A
--
9
6
$3,000
B
8
5
$3,500
C
15
10
$4,000
D
B,C
3
$2,000
E
$2,500
F
D,E
2
1
$5,000
As with the other test problems, you must show your work to receive full credit.
a) What are the normal project completion time and the critical path?
b) What activity(ies) should be crashed to reduce the completion time found in a) by one week? What activity(ies) should be crashed if you want to reduce the completion time found in a) by six weeks?
c) Bragg's loses $3,500 in profit per week for every week the bakery is not completed. How many weeks will the project take if the bakery is willing to pay the crashing cost as long as it is economically the right decision?
d) What is the project completion time if all activities are crashed to their minimum Crash Time? Also, ignoring the $3,500 lost profit in c), what is the total additional cost incurred for crashing all of the activities to their minimum Crash Time compared to the Normal Times?
An analysis of the holding costs, including the appropriate annual holding cost rate.
For this assignment, you must submit a memo consisting of 900-1,300 words in which you discuss your experience using the 3 decision-making models.
A company produces two products which are processed on two assembly lines. Assembly line 1 has 100 available hours, and assembly line 2 has 42 hours. Propose linear programming model for this problem.
Write a two page summary on a particular process in any organization.
Determine the problem as stochastic dynamic programming problem. Specify phases, states, decisions and the optimal value function.
Graph the constraints for this problem. Indicate all feasible solutions. Find out the optimal solution to LP Relaxation. Round down to find out a feasible integer solution. Is this solution optimal?
Select a real company (not a retailer). Identify four decisions that the company makes at different levels of the organization. Explain the policies, procedures and decision-making tools which might be used to make each of the four decisions.
Evaluate your priority sequences in a) on average flow time from now, average lateness (with no credit for being early) and average days early (with zero days early for a job that is late).
The Wiethoff Company has a contract to produce 10000 garden hoses for a customer-Because these machines are from different manufacturers and employ differing technologies, their specifications are not the same.
Find a business or organization, preferably one where you are working used to work, or know an employee or owner. (You can use anything such as retail or finance departments)
How do you see the basic principles of project management aiding the operations manager/manageress in introducing change to the system/ process?
South Central Utilities has just announced the August 1 opening its second nuclear generator at its Baton Rou, Louisiana, nuclear power plant. Propose this staffing problem using LP. Solve problem. How many trainees should begin each month?
Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!
whatsapp: +1-415-670-9521
Phone: +1-415-670-9521
Email: [email protected]
All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd