An assembly line with 60 activities is to be balanced. The total amount of time to complete all 60 activities is 60 minutes. The longest activity takes 2.0 minutes and the shortest takes 0.4 minute. The line will operate for 540 minutes per day.
What are the maximum and minimum cycle times? Round your answers to one decimal place.
Maximum cycle time: ____minutes
Minimum cycle time: ____ minutes
How much daily output will be achieved by each of those cycle times? Round your answers to the nearest whole number.
Daily output achieved by maximum cycle time: ____units/day
Daily output achieved by minimum cycle time: _____units/day
Blue Computers, a major server manufacturer in the United States, currently has plants in Kentucky and Pennsylvania. The Kentucky plant has a capacity of 1 million units a year, and the Pennsylvania plant has a capacity of 1.5 million units a year. I..
What are some of the primary reasons people resist change? What are some of the ways a team leader can ensure that change is accepted or at least not resisted? Compare and contrast formal groups and informal groups. Explain the importance of leadersh..
Promotional decisions for Fitness supplements–Controls for Fitness supplements
Explain what accounting is. What is an account?
Analyze at least three potential management conflicts that may arise due to the identified differences and propose solutions for each to help combat.
According to the IBM Knowledge Center, risk indices are used to calculate risk probability and risk impact.
Analyze the data using a median run test and an up/down run test. What can you conclude? Test Conclusion Median Up/Down.
the warehouse manager thought your presentation on operations management was extremely valuable to the company. he now
What is meant by “Critical Supply Chain(s) (CSC): Supplier certification should decrease/increase Quality:
Using the dummy variable approach, forecast sales for January through December of the fourth year.
Provides the higher Gross Profit figure. Provides the most information for control purposes,
Determine two to three (2-3) methods of using stocks and options to create a risk-free hedge portfolio can be created.
Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!
whatsapp: +1-415-670-9521
Phone: +1-415-670-9521
Email: [email protected]
All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd