What are the expected completion time

Assignment Help Computer Engineering
Reference no: EM13809375

1. When buyers purchase new houses, they are frequently responsible for installing their own landscaping. The PERT/CPM network shown in the accompanying figure represents a landscaping project for a new home in Jackson, Mississippi. The times are in days.

a. What are the expected completion time and the critical path for the landscaping project?
b. What are the earliest and latest start and finish times for activity C?
c. How long can activity A be delayed without delaying the minimum completion time of the project?
d. If activities A, C, and F are each delayed three days, how long will the landscaping project be delayed?

2. Virtual Golf, Inc. (VGI) is contemplating introducing a new virtual reality golf experience that would, if successful, be located in many amusement parks and entertainment centers throughout the country. If the project gets the "go ahead", it must be completed within 20 weeks (140 days) to be installed in the Mall of America in Bloomington, Minnesota, for test marketing. The table below gives cost and time estimates (in days) for the activities of the project.

Activity

Immediate Predecessors
A. Feasibility study
-
B. Input from golf professionals
A
C. Conceptual design
B
D. Professional Feedback
C
E. Final design
D
F. Manufacture of unit
E
G. Software development
E
H. Equipment/software coordination
F,G
I. In-house unit testing
H
J. Operator training
H
K. Construct unit in mall store
I, J
L. Testing of unit in mall store
K

Activity
Normal Days
Crash Days
Normal Cost
Crash Cost
A. Feasibility study
14
12
$15,000
$17,500
B. Input from golf professionals
14
11
$55,000
$64,000
C. Conceptual design
8
8
$50,000
$50,000
D. Professional Feedback
12
9
$40,000
$50,000
E. Final design
18
16
$50,000
$65,000
F. Manufacture of unit
20
16
$40,000
$55,000
G. Software development
14
10
$55,000
$70,000
H. Equipment/software coordination
21
19
$25,000
$65,000
I. In-house unit testing
10
8
$25,000
$32,000
J. Operator training
21
21
$50,000
$50,000
K. Construct unit in mall store
9
6
$25,000
$40,000
L. Testing of unit in mall store
15
10
$10,000
$40,000

a. What is the minimum project cost that will allow the project to be completed within 21 weeks?

b. What is the minimum project cost that will allow the project to be completed within 19 weeks?

3. Consider the project facing VGI in Problem 2. If the company allocated a maximum of $450,000 to this project, what is the minimum time it would take to complete the project?

4. Universal Travel is planning to move its headquarters from Cincinnati to Columbus, Ohio. The table below details the steps that must be taken. Times are in weeks.
Immediate Predecessors
Optimistic Time
Most Likely Time
Pessimistic Time
A. Select a site
-
8
12
20
B. Refurbish building
A
9
10
12
C. Determine which staff will transfer
-
2
2
3
D. Hire staff replacements in Columbus
C
3
6
8
E. Pack boxes in Cincinnati
A,C
1
2
5
F. Move equipment
B
2
3
4
G. Move files
B,E
1
2
5
H. Set up equipment/files in Columbus
F,G
3
4
5
I. Occupancy
D,H
5
6
10

a. What is the expected completion time of the project? What is the critical path?

b. What is the probability the project will be completed within 36 weeks?

c. Suppose Universal will be charged for both sites if it is not completely moved in within 36 weeks. This will cost the company $5,000.

The company is considering two options to improve its chances to meet this deadline.
- For $1,000, additional movers can be hired to move the files. This would cut each of the three time estimates for that activity in half.
- Additional movers can be hired for $1,000 to assist in moving the equipment. This would cut the three time estimates for that activity by one week each.
The company can pursue either OR BOTH of these options. What is your recommendation?

Reference no: EM13809375

Questions Cloud

Find mean standard deviation and coefficient of variation : work out the mean, standard deviation and coefficient of variation for each set of results. comment on the accuracy and precision of your results
What are some options for accomplishing in a lawful manne : What are some options for accomplishing this goal in a lawful manne
Theories of change management : Discuss at least 3 theories of change management (eg. Kotter, Lewin, Nadler, action research, and appreciative inquiry). Include specific pros and cons of each.
Find the mean price of a book of statistics or mathematics : Suppose a sample of 10 statistics books gave a mean price of $ 48 and a sample of 8 mathematics books gave a mean price of $ 49. Find the mean price of a book of statistics or mathematics
What are the expected completion time : What are the expected completion time and the critical path for the landscaping project and What are the earliest and latest start and finish times for activity C
What is the best central measure and the best dispersion mea : In a sample of 30 students of the Academy, we obtained the following data which represents the weights of these students 65, 59, 47, 67, 56, 50, 74, 45, 83, 72, 71, 53, 82, 58, 64 79, 55, 88, 56, 69, 50, 68, 66, 62, 59, 52, 72, 63, 56, 91 Answer the ..
Analyze the federal acquisition regulation : Analyze the FAR, and conclude whether or not these regulations overall offer adequate protection of the collective buying power of the American people. Prepare an argument in support of your position.
Distinguish between functional and psychological needs : Distinguish between functional and psychological needs. Identify 1 product that would fulfill each need for you and explain how it fulfills your need.
What is foreign aid and what is the goal of foreign aid : What is foreign aid and what is the goal of foreign aid?

Reviews

Write a Review

Computer Engineering Questions & Answers

  Mathematics in computing

Binary search tree, and postorder and preorder traversal Determine the shortest path in Graph

  Ict governance

ICT is defined as the term of Information and communication technologies, it is diverse set of technical tools and resources used by the government agencies to communicate and produce, circulate, store, and manage all information.

  Implementation of memory management

Assignment covers the following eight topics and explore the implementation of memory management, processes and threads.

  Realize business and organizational data storage

Realize business and organizational data storage and fast access times are much more important than they have ever been. Compare and contrast magnetic tapes, magnetic disks, optical discs

  What is the protocol overhead

What are the advantages of using a compiled language over an interpreted one? Under what circumstances would you select to use an interpreted language?

  Implementation of memory management

Paper describes about memory management. How memory is used in executing programs and its critical support for applications.

  Define open and closed loop control systems

Define open and closed loop cotrol systems.Explain difference between time varying and time invariant control system wth suitable example.

  Prepare a proposal to deploy windows server

Prepare a proposal to deploy Windows Server onto an existing network based on the provided scenario.

  Security policy document project

Analyze security requirements and develop a security policy

  Write a procedure that produces independent stack objects

Write a procedure (make-stack) that produces independent stack objects, using a message-passing style, e.g.

  Define a suitable functional unit

Define a suitable functional unit for a comparative study between two different types of paint.

  Calculate yield to maturity and bond prices

Calculate yield to maturity (YTM) and bond prices

Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd