Reference no: EM132774401
Suerte Company has a process cost system. All materials are introduced at the beginning of the process in Department 1. The following information is available for the month of January 2020:
Work in process 1/1,2020 (40% completed as to conversion cost) 500
Started in January 2,000
Transferred to Department II during January 2,100
Work In process 1/31/20 (25% conversion cost) 400
Problem 1: What are the equivalent unit production for the month of January , 2020
FIFO AVERAGE
MATERIALS CONVERSION MATERIALS CONVERSION
a. 2,500 2,200 2,000 2,000
b. 2,500 1,900 2,500 1,900
c. 2,000 2,200 2,000 2,200
d. 2,000 2,000 2,500 2,200