Reference no: EM131302854
Problem 1. A project in its 26th week has an actual cost of $270,000. It was scheduled to have spent $261,000. For the work performed to date, the budgeted value is $272,000. What are the cost and schedule variances for the project? What are the SPI and CPI?
Problem 2. A project has just completed its 87th item in the project plan. It was scheduled to have spent $168,000 at this point in the plan, but has actually spent only $156,000. The project manager estimates that the value of the work actually finished is nearly $162,000. What are the spending and schedule variances for the project? What are the SPI and CPI?
Problem 3. The following project is at the end of its 6th week. Find the cost and schedule variances. Also find the CPI and SPI. Then find the critical ratio of the project using earned value calculations. Finally, calculate the ETC and EAC for the project.
Activity
|
Predecessor
|
Duration (wks)
|
Budget ($)
|
Actual Cost ($)
|
%Complete
|
a
|
-
|
2
|
300
|
400
|
100
|
b
|
-
|
3
|
200
|
180
|
100
|
c
|
A
|
2
|
250
|
300
|
100
|
d
|
A
|
5
|
600
|
400
|
20
|
e
|
b,c
|
4
|
400
|
200
|
20
|
Problem 4.
Using the concepts from Session 11 reading (textbook and reserved readings), respond to following with a thorough explanation. Include any citations for references used to support your answer.
1. What are some reasons that a failing project still might not be terminated?
2. Who would make the best auditors: outside unbiased auditors or inside auditors who are more familiar with the organization, its procedures, and the project? Why?
3. Under what circumstances would you change your answer to the previous question?
4. Should the results of an evaluation or audit be shared with the project team?
5. What are the major purposes served by an after-the-fact project evaluation?
Problem 5. Solve the following Case:
Stoneworth Paving Company specializes in highway paving jobs for state of Virginia. When the State first awarded Stoneworth the contract, they stipulated a 1% penalty for each week Stoneworth was late on a completion date. Preston Flintrock, the project coordinator for Stoneworth, began to notice that the last two jobs were three weeks late, and the paving job that was due to be completed in the next two weeks was behind schedule. When Preston went in the field to investigate, he found the job to be understaffed, supplier delays, and a high work rejection/repaving needed. As a result, Preston decided to establish a better system of project control and present it to the boss.
Question 1: If you were Preston, what characteristics would you be looking for in a new control system? Explain
Question 2: Will a new control system be adequate for the problem? Explain
What is the cross-rate of swiss francs to euros
: Suppose the exchange rate between U.S. dollars and Swiss francs is SF 1.143 = $1.00, and the exchange rate between the U.S. dollar and the euro is $1.00 = 1.1033 euros. What is the cross-rate of Swiss francs to euros (SF/Euro)? Enter your answer roun..
|
What are the total shortage costs
: ABC Company sells 2,995 chairs a year at an average price per chair of $198. The carrying cost per unit is $27.77. The company orders 330 chairs at a time and has a fixed order cost of $31 per order. The chairs are sold out before they are restocked...
|
What are organizational controls
: What is organizational structure and what are organizational controls? What are the differences between strategic controls and financial controls? What is the importance of these differences?
|
Do businesses have social responsibilities
: Do businesses have social responsibilities? Why or why not? What can be some social aspects of businesses?
|
What are the cost and schedule variances for the project
: Problem 1. A project in its 26th week has an actual cost of $270,000. It was scheduled to have spent $261,000. For the work performed to date, the budgeted value is $272,000. What are the cost and schedule variances for the project? What are the S..
|
What type of adjustments must advertising agencies make
: What type of adjustments must advertising agencies make as more companies want "one sight, one sound, one sell" campaigns? Use examples if possible.
|
Lowers expected rate of return on foreign currency deposits
: Briefly explain your answer. No credit without explanation. Support your answer with a graph if needed. Depreciation of the domestic currency today (i.e. EH/F in class) lowers the expected rate of return on foreign currency deposits.
|
Propose a type of message appeal to be used in advertising
: Propose a type of message appeal to be used in the advertising, making sure to explain rationale behind appeal. Analyze different cultures product will appeal to and make recommendations on which three would be best choice.
|
How can you assess and address risk factors
: Can risk be eliminated if the project is well and carefully planned? How do you calculate acceptable risks? How can you assess and address risk factors? Please explain. Use a specific example to support your answer.200 words
|