What are the benefits of proper classification of materials

Assignment Help Civil Engineering
Reference no: EM133341632

Construction Technology And Management - Construction Engineering And Management

Part 1:

Question 1: project network has five paths-P1, P2, P3, P4 and P5. The total activity duration computed along each of these paths are-22, 31, 20, 30 and 19 days, respectively. What is the minimum duration for project completion?

Question 2: The early occurrence time and the late occurrence time of the starting event of an activity are 10 and 12, respectively. The early occurrence time and the late occurrence time of the finishing event of the same activity are 22 and 26, respectively. If the estimated duration for the activity is 10 time units, what is the total float available for the activity?

Question 3: Two project activities ‘A' and ‘B' (B being dependent on A) have a finish-finish relationship with 8 days ‘lag'. The estimated durations for the activities are 10 days and 15 days, respectively. Ifactivity ‘A' is scheduled to start on the 12th day from the beginning of project, on which day can you schedule to start activity ‘B'?

Question 4: For the network shown in Figure Q6.5.1:
(a) What are the critical path and the project duration?
(b) If the estimated duration for activity ‘C' is revised to 8 days, will the critical path remain the same as earlier?

Question 5: You have to construct a building to set up your office. You own a plot of 100 square yards (30 feet 3 30 feet) in a prime location. For the time being, you are in a position to construct ground floor alone due to financial constraints. So, you have decided to construct a simple RC structure. It consists of individual footing for 16 columns (columns are spaced every 10 feet in both directions) and a plinth beam at about 1 m from the existing road level. All the columns are going up to roof level, and you plan to have an RC roof slab and beam. The in between space is constructed by using locally available bricks. There is earth filling up to plinth level, and after proper compaction of filled-up earth, flooring is laid. Other activities includeplastering, painting, doors and windows, plumbing and electrical work. For your ready reference, the estimated duration for individual activities and their dependence are listed in Table Q6.17.1. How much time will it take to construct the building?

Part 2: Project Scheduling and Resource Levelling.

Question 1 A construction company has been awarded a contract to construct a flyover in a city with a completion period of 18 months. The major activities in the project and the relationships among them, the normal and crash durations, and the corresponding normal and crash costs are given in Table Q7.1.1...

(i) If the project attracts a penalty of ` 10,000 per month for project completion beyond 18 months, find out the total project cost including penalty if the company does not ‘crash' any activity.
(ii) Which of the activities should be crashed first in order to reduce the penalty payable and reduce thetotal cost?

Question 2 The precedence requirements, normal and crash activity times, and normal and crash costs for a construction project are given in Table Q7.2.1. The overhead costs are ` 4 lakh per week.
(i) Find the critical path and time for completion under normal working conditions.
(ii) Find the optimum duration for the project to minimize the total project cost. What is the total project cost for the optimum duration?

Part 3: Construction Materials management.

Question 1. What are the benefits of proper classification of materials?

Question 2. What are the inventory-related costs? What are the functions of inventories?

Question 3. Why are inventory models needed? Discuss EOQ model.

Reference no: EM133341632

Questions Cloud

Disorders may be diagnosed by colonoscopy : Which of the following disorders may be diagnosed by colonoscopy? Which of the following disorders would most likely be treated with antibiotic medication?
How can be utilize one or more of microsoft office programs : how can be utilize one or more of the microsoft office programs taught to assist with planning the upcoming holiday season or kicking off the New Year starting
What is the cooperative conclusion : Determine the Nash equilibrium of this game; What is the cooperative conclusion? What happens to the outcome of this game if this game is played repeatedly?
Why are rent controls inefficient : Why are rent controls inefficient? What is the market failure that occurs when rent controls are imposed? Put economic theory aside for a moment.
What are the benefits of proper classification of materials : What are the benefits of proper classification of materials and What are the inventory-related costs? What are the functions of inventories
What are two reasons why a country might engage in this type : Canada and China have decided to both engage in the trade of bikes to one another. What kind of trade is this? What are two reasons why a country might engage
Discuss the importance of advocacy : Discuss the importance of advocacy as it pertains to client care. What is the nurse's role in client advocacy?
Determine the profit-maximizing uniform price and quantity : Determine the profit-maximizing uniform price and quantity and calculate total profit. Determine how much potential profit is left "on the table"
Compare the demand conditions in each market : Compare the demand conditions in each market; i.e. how do the two markets differ in their demand for the firm's product?

Reviews

Write a Review

Civil Engineering Questions & Answers

  What is the soils unit weight when the degree of saturation

A dry quartz sand has a unit weight of 100 pcf. What is the soil's unit weight when the degree of saturation is 75% if Gs = 2.66

  Determine what is the decrease in thickness of the 6-ft fill

A loose, uncompacted sand fill 6 ft in depth has a relative density of 40%. Laboratory tests indicated that the minimum void ratios of the sand are 0.46 and 0.90, respectively. The specific gravity of solids of the sand is 2.65.

  Determine the coordinates of intersection of line of action

Replace the given forces by a wrench and determine the coordinates of the intersection of its line of action (the coordinate of point P) with the plate. With a Force Fca=(100i+100j)N coming off of point C

  Calculate the velocity in the constriction and the flowrate

Water flows through a 75 mm constriction in a horizontal 150 mm pipe. If the pressure in the 150 mm section is 345 kPa and that in the constriction 207 kPa, calculate the velocity in the constriction and the flowrate.

  What are the names of the towns located in strafford county

This project assignment will provide you with an opportunity to use ArcMap software to analyze a "hypothetical" situation using GIS data

  Possible saturated hydraulic conductivity combinations

Provide an example of aquifer and geologic properties that lend to one of the four possible saturated hydraulic conductivity combinations of heterogeneity

  Determine the mass and the stiffness of the system

At an excitation frequency of 4 Hz, the response tends to increase without bound(ie a resonant condition). Next, a weight of deltaW= 5lb is attached to the mass m and the resonance test is repeated.

  What maximum force can this person apply with the jack

A person of mass 80kg places all their weight on the pedal of a foot operated hydraulic jack. The diameter of the hydraulic cylinder under foot pedal is 4cm and the diameter of the jack cyclinder is 9cm (Assume g is 9.81 m/s^2)

  Describe what is the definition of a friend function

Provide the function prototype for the following function if it is to be declared as a friend function of class Planet. Include the class declaration and the proper access attribute, but you are not required to add any additional class data or fun..

  Determine the weight of the gate per meter of length

The homogeneous gate shown consists of one quarter of a circular cylinder and is used to maintain a water depth of 4m. That is, when the water depth exceeds 4m, the gate opens slightly and lets the water flow under it. Determine the weight of the gat..

  Which objects are used in raster format representations

Name and describe the different simple spatial objects used for representing graphic data in digital form.Which objects are used in raster format representations?

  Determine the normal depth-velocity and the froude number

A PVC pipe with a diameter of 30 inches will carry a flow of 20 cfs. the bottom slope is 0.005 and the roughness coefficient is 0.015. determine the normal depth, critical depth, velocity and the froude number.

Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd