What are some of issues that a co must consider to ensure

Assignment Help Business Management
Reference no: EM131596478

Learning Activity 1

Modifications allow the CO a broad range and ability to change a contract. What are some of the issues that a CO must consider to ensure that contract mod is "within scope"?

Response 1:

A CO must be sure to understand what the overall scope of the contract is. If too different of a modification is done, it is possible for a Bid Protest by a 3rd party. This would challenge the government CO for making an out-of-scope modification. Additionally, current contract agreements may have a contract dispute for any changes that the government makes to their current contract that significantly changes the contract from the original agreement. (Contract & Fiscal Law Department, 2013)

There are several tests the GAO has to test modifications to contracts. Would the modification really change the contract from when it was originally awarded, could the change have been seeable by companies looking to bid, where the companies advised about the changes prior to the changes, and other tests. (Contract & Fiscal Law Department, 2013)

Response 2:

Some of the issues that a CO must consider when changing a contract are cost, is the contract allowed to have changes and also is the change in direct relation to the work that has been agreed upon initially.

First and foremost, the funding cannot be increased unless there is a certification of fund availability (FAR, 2017).

Secondly, the contract must initially state that the contract is allowed change orders. If this statement is not included into the initial contract, nothing can be done.

Lastly, the work that is specified in the new change order must be related to the work that was initially contracted out to make sure that it does not seem as the Government is not giving out work without competition.

Learning Activity #2

Contract Modifications are used to make changes to the award. They come in two types- Bilateral and Unilateral. Discuss each type and the types of changes that are specific to each.

Response 1:

A bilateral modification is used to make contract adjustments and/or changes. It also defines the letter contracts and shows further agreements by both parties that modify the contract. This modification is signed by the contractor and CO (FAR, 2017).

A unilateral modification is when changes are made to the contract that deals with administration. It can issue change orders that will add or delete work from the original contract. Other change clauses can also be authorized like property clause or suspension of work. When a contract is going to be terminated a unilateral modification can be used to issue termination notices. This type of modification only needs to be signed by the CO (FAR, 2017).

Response 2:

The two types of contract modifications are Unilateral modification, and Bilateral modification. The Unilateral modification is official upon the signature of the CO it does not however require the contractor's signature. This modification can be used to issue change orders, make administrative changes, as well as implementing terms and conditions previously authorized in the contract. The Bilateral modification is signed by the contractor and then by the CO. It's used to make negotiated equitable adjustments. It can be used tp change terms and conditions of a contact, definitive change orders, as well as negotiating equitable adjustments.

Learning Activity 1

What are some of the courses of action that a CO should consider before starting the termination of a contractor who is not performing well?
Response 1:

Some of the courses of action that a CO should consider before starting the termination of a contractor who is not performing well are: (FAR, 2017)

(b) The contracting officer shall terminate contracts, whether for default or convenience, only when it is in the Government's interest. The contracting officer shall effect a no-cost settlement instead of issuing a termination notice when-

(1) It is known that the contractor will accept one,
(2) Government property was not furnished, and
(3) There are no outstanding payments, debts due the Government, or other contractor obligations.

(c) When the price of the undelivered balance of the contract is less than $5,000, the contract should not normally be terminated for convenience but should be permitted to run to completion.

(d) After the contracting officer issues a notice of termination, the termination contracting officer (TCO) is responsible for negotiating any settlement with the contractor, including a no-cost settlement if appropriate. Auditors and TCO's shall promptly schedule and complete audit reviews and negotiations, giving particular attention to the need for timely action on all settlements involving small business concerns.

(e) If the same item is under contract with both large and small business concerns and it is necessary to terminate for convenience part of the units still to be delivered, preference shall be given to the continuing performance of small business contracts over large business contracts unless the chief of the contracting office determines that this is not in the Government's interest.

(f) The contracting officer is responsible for the release of excess funds resulting from the termination unless this responsibility is specifically delegated to the TCO.

Response 2:

According to DAU's website; these are the steps a Contracting Officer shall decide on what type of termination and consider these steps prior to the termination:

1. The terms of the contract and applicable laws and regulations.

2. The specific failure of the contractor and the excuses for the failure.

3. The availability of the supplies or services from other sources.

4. The urgency of the need for the supplies or services and the period of time required to obtain them from other sources, as compared with the time delivery could be obtained from the delinquent contractor.

5. The degree of essentiality of the contractor in the Government acquisition program and the effect of a termination for default upon the contractor's capability as a supplier under other contracts.

6. The effect of a termination for default on the ability of the contractor to liquidate guaranteed loans, progress payments, or advance payments.

7. Any other pertinent facts and circumstances.

Learning Activity #2

Once a contractor is notified that their contract is being terminated what are some of the things they should do? How does the type of termination affect the contractor's options?

Response 1:

Per the Federal Acquisition Regulation (FAR) 49.104 these are the steps the contractor should take once notified about the contract termination. "After receipt of the notice of termination, the contractor shall comply with the notice and the termination clause of the contract, except as otherwise directed by the TCO. The notice and clause applicable to convenience terminations generally require that the contractor--
(a) Stop work immediately on the terminated portion of the contract and stop placing subcontracts thereunder; (b) Terminate all subcontracts related to the terminated portion of the prime contract; (c) Immediately advise the TCO of any special circumstances precluding the stoppage of work; (d) Perform the continued portion of the contract and submit promptly any request for an equitable adjustment of price for the continued portion, supported by evidence of any increase in the cost, if the termination is partial; (e) Take necessary or directed action to protect and preserve property in the contractor's possession in which the Government has or may acquire an interest and, as directed by the TCO, deliver the property to the Government; (f) Promptly notify the TCO in writing of any legal proceedings growing out of any subcontract or other commitment related to the terminated portion of the contract; (g) Settle outstanding liabilities and proposals arising out of termination of subcontracts, obtaining any approvals or ratifications required by the TCO; (h) Promptly submit the contractor's own settlement proposal, supported by appropriate schedules; and (i) Dispose of termination inventory, as directed or authorized by the TCO." Additionally, any option years on a contract that have yet to be exercised will be null and void.

Response 2:

Once a contractor is notified that they are being terminated, there are many things that they have to do: (FAR, 2017)

(a) Stop work immediately on the terminated portion of the contract and stop placing subcontracts thereunder;

(b) Terminate all subcontracts related to the terminated portion of the prime contract;

(c) Immediately advise the TCO of any special circumstances precluding the stoppage of work;

(d) Perform the continued portion of the contract and submit promptly any request for an equitable adjustment of price for the continued portion, supported by evidence of any increase in the cost, if the termination is partial;

(e) Take necessary or directed action to protect and preserve property in the contractor's possession in which the Government has or may acquire an interest and, as directed by the TCO, deliver the property to the Government;

(f) Promptly notify the TCO in writing of any legal proceedings growing out of any subcontract or other commitment related to the terminated portion of the contract;

(g) Settle outstanding liabilities and proposals arising out of termination of subcontracts, obtaining any approvals or ratifications required by the TCO;

(h) Promptly submit the contractor's own settlement proposal, supported by appropriate schedules; and

(i) Dispose of termination inventory, as directed or authorized by the TCO.

Depending on the type of termination, a contractor may be authorized costs to shut their program down as well as a small profit (a), they may be reimbursed for any costs they have incurred if they are on a cost reimbursement contract (b) or if they are found to be in default they will not be paid for any work not performed and possibly transfer any remaining materials or supplies over to the government (c). (FAR, 2017)

Federal Acquisitions Regulation, 48 C.F.R. §49.104 (2017).

(a) Federal Acquisitions Regulation, 48 C.F.R. §49.201(a) (2017).
(b) Federal Acquisitions Regulation, 48 C.F.R. §49.301 (2017).
(c) Federal Acquisitions Regulation, 48 C.F.R. §49.402-2(a) (2017).

Reference no: EM131596478

Questions Cloud

What is the cash flow from assets : Precision Manufacturing had the following operating results for 2014: What is the cash flow from assets for 2014?
Portfolio effect in capital budgeting refers : The "portfolio effect" in capital budgeting refers to. Which of the following is NOT true about the life-cycle growth and dividend policy?
Discuss cops and pops : Community-oriented policing (COPS), problem-oriented policing (POPs), and the zero-tolerance policing concepts are three criminal justice policy initiatives.
Preparing a bank reconciliation as of june : Other information that may be relevant in preparing a bank reconciliation as of June 30, 2015, is as follows
What are some of issues that a co must consider to ensure : Modifications allow CO a broad range and ability to change contract. What are some of issue that a CO must consider to ensure that contract mod is within scope?
Write a java program - initialize a counter : Gets input for temperature Utilizing a branching statement: If temperature is 76-100, call method outputHot passing the temperature input as an argument.
Discuss range of issues and interactions in the family : This podcast is about family system crisis and the role of the police in this crisis. It is giving examples of a range of issues and interactions in the family.
Develop the first learning experience : Develop the first learning experience, addressing the categories of learning goals discussed in the readings and in the Discussion.
Define all relationships between entities : Create an entity-relationship diagram (ERD) from the entities - Define all relationships between entities

Reviews

Write a Review

Business Management Questions & Answers

  Caselet on michael porter’s value chain management

The assignment in management is a two part assignment dealing 1.Theory of function of management. 2. Operations and Controlling.

  Mountain man brewing company

Mountain Man Brewing, a family owned business where Chris Prangel, the son of the president joins. Due to increase in the preference for light beer drinkers, Chris Prangel wants to introduce light beer version in Mountain Man. An analysis into the la..

  Mountain man brewing company

Mountain Man Brewing, a family owned business where Chris Prangel, the son of the president joins. An analysis into the launch of Mountain Man Light over the present Mountain Man Lager.

  Analysis of the case using the doing ethics technique

Analysis of the case using the Doing Ethics Technique (DET). Analysis of the ethical issue(s) from the perspective of an ICT professional, using the ACS Code of  Conduct and properly relating clauses from the ACS Code of Conduct to the ethical issue.

  Affiliations and partnerships

Affiliations and partnerships are frequently used to reach a larger local audience? Which options stand to avail for the Hotel manager and what problems do these pose.

  Innovation-friendly regulations

What influence (if any) can organizations exercise to encourage ‘innovation-friendly' regulations?

  Effect of regional and corporate cultural issues

Present your findings as a group powerpoint with an audio file. In addition individually write up your own conclusions as to the effects of regional cultural issues on the corporate organisational culture of this multinational company as it conducts ..

  Structure of business plan

This assignment shows a structure of business plan. The task is to write a business plane about a Diet Shop.

  Identify the purposes of different types of organisations

Identify the purposes of different types of organisations.

  Entrepreneur case study for analysis

Entrepreneur Case Study for Analysis. Analyze Robin Wolaner's suitability to be an entrepreneur

  Forecasting and business analysis

This problem requires you to apply your cross-sectional analysis skills to a real cross-sectional data set with the goal of answering a specific research question.

  Educational instructional leadership

Prepare a major handout on the key principles of instructional leadership

Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd