What amount would the flexible budget

Assignment Help Managerial Accounting
Reference no: EM132607853

Pollitt Potato Packers has a flexible budget for manufacturing overhead that is based on direct labour hours. The following overhead costs appear on the flexible budget at the 200,000-hour level of activity:

Variable overhead costs (total):

Packing supplies $120,000

Indirect labour $180,000

Fixed overhead costs (total):

Utilities $100,000

Insurance $40,000

Rent $20,000

Problem 1: At an activity level of 180,000 direct labour hours, what amount would the flexible budget estimate for indirect labour cost?

A) $180,000.

B) $144,000.

C) $162,000.

D) $108,000.

Reference no: EM132607853

Questions Cloud

Most devastating elements : Fire is one of the most devastating elements that can destroy the physical components of an entity quickly.
Compute how many units must be produced during month : Pardee Company, on hand at start of the month, and plans to have 2,000 units on hand at the end of the month, how many units must be produced during the month?
How each step can be applied to your chosen dilemma : Choose a contemporary ethical dilemma at an organization that you are familiar with or find through research. Using the article, The PLUS ethical decision.
Security is very complex process-affecting applications : Security is a very complex process, affecting applications, networks, databases, facilities, and more. This week we will examine security considerations.
What amount would the flexible budget : Pollitt Potato Packers, At an activity level of 180,000 direct labour hours, what amount would the flexible budget estimate for indirect labour cost?
What would have been the rate of return : What would have been the rate of return to an investor who held the same securities as the fund manager during the year
Reflections about your experiences-attitudes and opinions : The journal is a record of reflections about your own experiences, attitudes, opinions, and feelings in relation to the material and within the context
What was the sales volume variance for february : What was the sales volume variance for February? Alaska Company expressed the total expenses (Y) component of its master budget for February
Create a training presentation on ethics and compliance : Based on the importance of transparency, your organization (you can represent any organization, McDonalds, Starbucks, ESPN, etc.) has asked you to create.

Reviews

Write a Review

Managerial Accounting Questions & Answers

  Manage budgets and financial plans

Explain the budgeting process and its importance to a business, identifying the components of different budgets, forecast estimates for inclusion in the budgets.

  Prepare a retained earnings statement

Prepare a retained earnings statement for the year and Prepare a stockholders' equity section of given case.

  Prepare a master budget for the three-month period

Prepare a master budget for the three-month period.

  Construct the companys direct labor budget

Construct the company's direct labor budget for the upcoming fiscal year, assuming that the direct labor workforce is adjusted each quarter to match the number of hours required to produce the forecasted number of units produced.

  Evaluate the predetermined overhead rate

Evaluate the Predetermined Overhead Rate

  Determine the company''s bid

Determine the company's bid if activity-based costing is used and the bid is based upon full manufacturing cost plus 30 percent.

  Compute the pool rates for the different activities

Complete the schedule to compute the pool rates for the different activities.

  Prepare Company financial statements

Prepare Company financial statements

  Prepare an analysis of terracycles

This individual assignment is based on the TerraCycle Inc.

  Discuss the ethical issues

Discuss the ethical issues

  Political resources in emerging markets

Calculate the GDP in Income Approach  and Expenditure Approach

  Management accounting - ehsan electronics company

A new plant accountant suggested that the company may be able to assign support costs to products more accurately by using an activity based costing system that relies on a separate rate for each manufacturing activity that causes support costs.

Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd