Reference no: EM1310940
Allocation of operating costs using single-rate cost-allocation method.
The AC Corporation operates one central plant that has two divisions, the Flashlight Division and the Night Light Division. The following data apply to the coming budget year:
Budgeted costs of the operating the plant for 10,000 to 20,000 hours:
Fixed operating costs per year
|
$240,000
|
Variable operating costs
|
$10 per hour
|
Practical capacity
|
20,000 hours per year
|
Budgeted long-run usage per year:
Lamp Division
|
800 hours × 12 months = 9,600 hours per year
|
Flashlight Division
|
450 hours × 12 months = 5,400 hours per year
|
Assume that practical capacity is used to calculate the allocation rates. Further assume that actual usage of the Lamp Division was 700 hours and the Flashlight Division was 400 hours for the month of June.
Required:
a.If a single-rate cost-allocation method is used, what amount of operating costs will be budgeted for the Lamp Division each month? For the Flashlight Division each month?
b.For the month of June, if a single-rate cost-allocation method is used, what amount of cost will be allocated to the Lamp Division? To the Flashlight Division? Assume actual usage is used to allocate operating costs.
c. If a dual-rate cost-allocation method is used, what amount of operating costs will be budgeted for the Lamp Division each month? For the Flashlight Division each month?
d.For the month of June, if a dual-rate cost-allocation method is used, what amount of cost will be allocated to the Lamp Division? To the Flashlight Division? Assume budgeted usage is used to allocate fixed operating costs and actual usage is used to allocate variable operating costs.