What activities are critical for established timeline

Assignment Help Project Management
Reference no: EM131564251

Discussion- Initial Post

Scenario: You are a consultant with expertise in project management strategies. Select a possible project management situation from your current or future professional experience. As a project management consultant, you are tasked with developing a project management plan for this project. Your goal is to maximize the time, resources and finances associated with the project in the best interests of the business/company. You will need to write a professional memo to the business/company owner describing the management of the project.

Use Excel QM to create the project. See video in Live Binder. Your professional memo should include:

1. Create the PERT/CPM activity network for your project that includes at least five activities and at least one predecessor activity.
2. Estimate the optimistic, most likely, and pessimistic times to then determine an expected time for each activity.
3. Determine all activities that are on the critical path.
4. Identify the slack time (if any) associated with activities in the project.
5. Create a Gantt chart to show the project timeline.

Address the following questions in your professional memo:

• What is the overall timeline for this project?
• What activities are critical for established timeline of the project?
• What activities have flexibility in completion that would not impact the overall project timeline?
• What time, resources and money might be affected by any changes to activities throughout the project?
• What recommendations would you suggest to prioritize the company's time, resources and money with regards to the project?

1 & 2) I am a project management expert tasked with managing a project in my current or future profession. I will suggest a course revision for a class. The time estimates are in weeks.

Tasks

optimistic

average

pessimistic

Predecessor

A - Select new textbook

4

6

10

 

B - Create unit assignments

5

8

12

A

C - Select topics for units

1

2

3

A

D - Set up gradebook

1

2

3

B

E - Review content

2

4

6

B

3) Activities on the critical path? All activities with slack time = 0 are on the critical path: A - Select new textbook, B - Create unit assignments, E - Review content

4) Slack time:

Results

 

 

 

 

 

Activity

Early Start

Early Finish

Late Start

Late Finish

Slack

A

0

6.333333

0

6.333333

0

B

6.333333

14.5

6.333333

14.5

0

C

6.333333

8.333333

16.5

18.5

10.16667

D

14.5

16.5

16.5

18.5

2

E

14.5

18.5

14.5

18.5

0

 

Project

18.5

 

 

 

5) Gantt Chart showing Early Start Times:

Now, using the above computations and write your discussion response as a professional memo.

1740_Gantt Chart.jpg

Reference no: EM131564251

Questions Cloud

Self-disclosure in various human and social services : Think about your current professional position or one you'd like to work in the future. Consider when you might and might not use self-disclosure.
Where did you obtain your advance directive forms : Where did you obtain your advance directive forms? How accessible were the documents? Do you believe that medical services should be rationed to the elderly?
Prescription drug product in the provided scenario : Describe one individual and one industry consumer for the prescription drug product in the provided scenario.
Determine the absolute minimum : SENIOR WORKFORCE The percentage of women 65 yr and older in the workforce from 1970 through the year 2000 is approximated by the function.
What activities are critical for established timeline : What activities are critical for established timeline of project? What activities have flexibility in completion that would not impact overall project timeline?
Stakeholders about the museum purpose and direction : How would you attempt to resolve the underying conflics among key stakeholders about the museum's purpose and direction?
Explain why you believe this grant would be beneficial : Identify one grant to use for this Journal Assignment. Think about human services programs for which this grant might be beneficial.
About inflation expectations : How can investors find out about inflation expectations?
Electrical malfunctions and software bugs : What steps would you recommend be taken to protect patients from the effects of computer viruses, electrical malfunctions, and software bugs?

Reviews

Write a Review

Project Management Questions & Answers

  Create a project schedule and align resources

Create a project schedule and align resources, Analyze project schedule and resource allocation

  Managerial roles and gap analysis

Write a report on Managerial Roles and Gap Analysis

  Questionaire on project management

Questionaire on Project Management

  Describe the market growth rate for product

Describe the market growth rate for product and service.

  Prepare a work plan and project schedule - gantt chart

Design an online system for the human resources department to manage available job positions.

  Project risk management approach

How does a project risk management approach pro-vide an early warning signal for impending problems or issues

  Black-scholes options pricing model

Calculate the payoff and the profits for investments

  Describe the features or characteristics of product

Describe the features or characteristics of your product or service.

  Write paper on inventory management system

Write paper on Inventory Management System.

  Analysis of the overall project risk

Analysis of the overall project risk

  Investment and performance analysis

Evaluate the usefulness of ROCE

  Distribution strategy and project management

Distribution strategy and project management

Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd