Reference no: EM13949206
Several years ago, Westmont Corporation developed a comprehensive budgeting system for planning and control purposes. While departmental supervisors have been happy with the system, the factory manager has expressed considerable dissatisfaction with the information being generated by the system.
A typical departmental cost report for a recent period follows:
Assembly Department Cost Report For the Month Ended March 31
|
|
Actual Results
|
Planning Budget
|
Variances
|
Machine-hours
|
|
25,000
|
|
30,000
|
|
|
|
Variable costs:
|
|
|
|
|
|
|
|
Supplies
|
$
|
7,500
|
$
|
8,100
|
$
|
600
|
F
|
Scrap
|
|
23,800
|
|
25,500
|
|
1,700
|
F
|
Indirect materials
|
|
72,200
|
|
84,000
|
|
11,800
|
F
|
Fixed costs:
|
|
|
|
|
|
|
|
Wages and salaries
|
|
70,300
|
|
67,000
|
|
3,300
|
U
|
Equipment depreciation
|
|
97,000
|
|
97,000
|
|
-
|
|
|
|
|
|
|
|
|
|
Total cost
|
$
|
270,800
|
$
|
281,600
|
$
|
10,800
|
F
|
|
|
|
|
|
|
|
|
|
After receiving a copy of this cost report, the supervisor of the Assembly Department stated, "These reports are super. It makes me feel really good to see how well things are going in my department. I can't understand why those people upstairs complain so much about the reports."
For the last several years, the company's marketing department has chronically failed to meet the sales goals expressed in the company's monthly budgets.
Required:
1. The company's president is uneasy about the cost reports, what can be the reason? (You may select more than one answer. Single click the box with the question mark to produce a check mark for a correct answer and double click the box with the question mark to empty the box for a wrong answer.)
|
Cost reports are ineffective since budgeted costs at one level of activity are compared to actual costs at another level of activity.
|
|
Cost reports show whether fixed costs are controlled and do not show whether variable costs are controlled.
|
|
Cost reports are effective since budgeted costs at one level of activity are compared to actual costs at another level of activity.
|
|
Cost reports show whether fixed costs and variable costs are controlled.
|
2. What kind of reports should be used to give better insight into how well departmental supervisors are controlling costs?
|
Flexible budget performance reports must be used
|
|
Fixed budget performance reports must be used
|
3. Complete the new performance report for the quarter, based on Flexible Budget Performance approach.(Indicate the effect of each variance by selecting "F" for favorable, "U" for unfavorable, and "None" for no effect (i.e., zero variance). Input all amounts as positive values.)
4. Were costs well controlled in March?
|
Costs were well controlled
|
|
Costs were not well controlled
|
Why do the lines differ in shape
: Plot the value of Progressive, with and without the costs of financial distress, as a function of the amount of debt. Why do the lines differ in shape?
|
Compute the following probabilities
: Given that z is a standard normal random variable, compute the following probabilities.
|
Gabby purchased a new home
: Gabby purchased a new home for $500,000 by making a down payment of $200,000 and financing the remaining $300,000 with a loan, secured by the residence, at 6%. In 2012.
|
Mountain view hospital
: Mountain View Hospital has purchased new lab equipment for $238,296. The equipment is expected to last for three years and to provide cash inflows.
|
Westmont corporation developed a comprehensive budgeting
: Westmont Corporation developed a comprehensive budgeting system for planning and control purposes. While departmental supervisors have been happy with the system
|
How does standard costing improve the control function
: How does standard costing improve the control function? Discuss the differences among actual costing, normal costing, and standard costing.
|
Write an analysis of a key character in a literary work
: Write an analysis of a key character in a literary work. Describe two to three key actions of the character, or how the character responds to events
|
Issues in higher education is attached below
: Review the case study that you selected (Casestudy 2: Issues in Higher Education is attached below) as well as the required module Learning Resources. Be sure to review the optional resources as you may find them equally helpful for this Assignmen..
|
When should a standard cost variance be investigated
: When should a standard cost variance be investigated? Explain why the materials price variance is often computed at the point of purchase rather than at the point of issuance.
|