Blue Hills has become a popular skiing destination in the Boston area. It is conveniently located close to the city and has some difficult paths for not being a large hill. The owners have been hoping to further capitalize on their proximity to Boston by building up additional ski slopes and a new Lodge. The results of an economic feasibility study just completed by members of the staff show that a winter resort complex near the base of the hill could be a very profitable venture. The hope is that the new buildings and slopes could be put in place this summer during the off-season so that the Lodge and new paths can open by late Fall 2018. The board has decided that construction should begin no later than April 1 and be completed by October 1, in time for the next skiing season. You have been assigned the task of project manager, and it is your job to coordinate the ordering of materials and construction activities to ensure the project's completion by the required date. The sub-projects are: a lodge, a new chair lift, and a new generator house.

After looking into the possible sources of materials, you are confronted with the following time estimates. Materials for the chair lift will take 30 days, to arrive once the order is submitted. Lumber for the lodge, generator hut, and foundations for all buildings will each take 9 days to arrive. The electrical and plumbing materials for the lodge will take 12 days to arrive. The generator will take 12 days to arrive. Before actual construction can begin on the various facilities, a road to the site must be built; this will take 6 days. As soon as the road is in, clearing can begin concurrently on the sites of the day lodge, generator house, and chair lift. It is estimated that the clearing task at each site will take 6 days, 3 days, and 36 days respectively. The clearing of the main ski slopes can begin after the area for the chair lift has been cleared; this will take 84 days.

The foundation for the day lodge will take 12 days to complete. Construction of the main framework will take an additional 18 days. After the framework is completed, electrical wiring and plumbing can be installed concurrently. These should take 24 and 30 days, respectively. Finally, the finishing construction on the day lodge can begin; this will take 36 days.

Before the chair lift towers can be installed, the site must be cleared, lumber delivered, and the foundation completed (6 days total).This step can be begun once the area for the chair lift itself has been cleared. The installation of the chair lift towers should be completed in 67 days. While the towers are being installed, the electric motor to drive the chair lift can be installed (24 days). Once the towers are completed and the motor installed, it will take 3 days to install the cable and an additional 12 days to install the chairs.

The foundation for the generator house can begin at the same time as the foundation for the lodge; this will take 6 days. The main framework for the generator house can begin once the foundation is completed; framing will take 12 days. After the house is framed, the diesel generator can be installed in 18 days. Finishing construction on the generator house can now begin and will take 12 more days.

1. Create some sort of visual representation of the activity on node network. This can be a picture of a pen and paper drawing or an electronic picture, whatever is easiest for you.

2. Identify the critical path on your network picture. Which is the critical path? [Note: the critical path is the dependent sequence of tasks which will take the longest to complete.]

3. Can the project be completed by October 1? If you make assumptions (such as working on the weekend or through holidays) be sure to identify them.

Reference no: EM132126722

Questions Cloud

Cost of jump is equal to the marginal cost for each firm : Suppose parachuting is a competitive market, so the cost of a jump is equal to the marginal cost for each firm.
What about example where it was not effective : Can you think of an example where you used that style and it was effective? What about an example where it was not effective?
Digital interaction-human contact into networking efforts : What’s the best way to incorporate both digital interaction and human contact into your networking efforts?
Several funding agencies publish call for research proposals : Research is a part of NC State. Several funding agencies publish call for research proposals (CFP) that are targeted towards academics to apply for grants.
Visual representation of the activity on node network : Create some sort of visual representation of the activity on node network. This can be a picture of a pen and paper drawing or an electronic picture,
What drives your decision between debt or equity instruments : What drives your decision between debt or equity instruments?
Why do you think starbuck and chipotle do not do franchising : Why do you think Starbucks and Chipotle don’t do franchising? What are the advantages of maintaining company-owned stores?
Important factors driving your choice of business entity : What are the 2 most important factors driving your choice of business entity? Why are these the 2 factors most important to you?
Process for health care improvement in health organizations : What is a major strength and major weakness of the Baldridge award process for health care improvement in health organizations?

Reviews

Write a Review

Operation Management Questions & Answers

  How an organization interacts with its environment

The case study discusses the dynamics of the global EV industry and Volkswagen's efforts to challenge Tesla's supremacy.

  Different what-if future alternatives-develop strategic plan

When managers envision different "what-if" future alternatives and develop strategic plans to address them, they are engaging in scenario planning. The process of planning scenarios can be considered a microcosm of the overarching framework of this t..

  Enhance employee jobs skill variety-task identity-autonomy

The job characteristics model has five components that enhance employee jobs skill variety, task identity, task significance, autonomy, and feedback. Give an example illustrating how each component can be used to improve the organization and the job ..

  Changes in the environmental bounds and managerial bounds

To design a “Zero Based Channel” what actions do you need to take as a channel designer? What impact it has on the positioning of the channel The choice of the Channel Structure Channel membership and their identity Exploring the idea of multiple cha..

  Ineffectiveness was caused by bad management

Provide examples of ineffective managers and leaders from your work experience. Do you think their ineffectiveness was caused by bad management, or bad leadership? Why?

  Determine the value-added ratio

Williams Optical Inc. is considering a new lean product cell. The present manufacturing approach produces a product in four separate steps.

  Examine how the concept translate thought into action

Examine how the concept “translate thought into action” bears on the relationship between business strategy

  The operations strategy for an organization

The operations strategy for an organization. Qualitative forecasting methods are used when. Quality is defined as.

  Describe and explain the six steps in contract management

Describe and explain the six steps in the contract management process for the buyer. Make sure to define each of the three phases of the process.

  Construct a plan for implementing change

Select an organization to plan for implementing change as an example company for your presentation to illustrate your ideas.

  What are the potential costs and benefits associated

What are the potential costs and benefits associated with allowing for intellectual property rights?

  Manager can apply takeaways from business ethics course

Personally reflect on how you as a supervisor/manager can apply "takeaways" from a business ethics course

Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd