From your previous work experiences and reference manuals, review the basic methodology associated with the PERT project management approach (using calculated values of task variance and task expected time for each task).
a. Find the te (expected task times) and the task variances for each of project tasks.
A) V=0 te=2 Q)V=0.1 te=3
B) V=0.1 te=3 R)V=0.1 te=2.3
C) V=0.1 te=2 S)V=0.0625 te=1.083
D) V=0.027 te=2.16 T)V=0.25 te=3.16
E) V=0.1 te=3 U)V=0.027 te=2.16
F) V=0 te=2
G) V=1 te= 15
H) V=1.361 te=15.83
I) V=1.361 te=17.83
J) V=1.362 te=22.16
K) V=0.1 te=2.3
L) V=0.027 te=2.16
M) V=0.4 te=4
O) V=0.0625 te=1.083
P) V=0.09 te=1.03
b. What is the critical path of the project, based on the new te values?
c. What is the sum of the variance values for the tasks on the critical path?
d. Without crashing tasks, what is the likelihood of completing the project on or before week 39 of the project?
e. Without crashing tasks, what is the likelihood of completing the testing (an important milestone in the project) before the end of week 37 of the project?
How many of the aspects of health services finance
: How many of the aspects of health services finance that we have explored this semester come together with current industry trends.
|
Risk involved in establishing and running sportswear shop
: Identify the various risk involved in establishing and running a (Sportswear Shop)
|
Failure to warn as they relate to strict liability and tort
: Explain in detail and give examples of design defects and failure to warn as they relate to strict liability and tort.
|
Current social media platform-twitter-facebook-linkedin
: Choose a current social media platform (Twitter, Facebook, Linkedin, Xing, Google+, Snapchat, Pinterest, Tumblr, YouTube, etc.).
|
Variance values for the tasks on the critical path
: What is the sum of the variance values for the tasks on the critical path?
|
Venture capital firm with substantial resources
: You have an opportunity as expert (and very expensive) consultant to help with e-business startup funded by a venture capital firm with substantial resources.
|
Current marketplace across the competitive set and beyond
: Research existing campaigns in the current marketplace across the competitive set and beyond.
|
Define one business process model relevant to the product
: Using BPMN, define one business process model relevant to the product (choose between sales, manufacturing, maintenance, service, etc.)
|
Safety and health at work
: Do you think Ming is correct in saying Mindy is bullying her? What are the indications of bullying?
|