Reference no: EM132236174
1. Which of the following are valid reasons for scheduling resources? (You may select more than one answer. Single click the box with the question mark to produce a check mark for a correct answer and double click the box with the question mark to empty the box for a wrong answer.)
To check if existing resources are adequate and available.unchecked
To decide which resources have priority.unchecked
To determine where the real slack is. unchecked
To decide if an imposed project duration is realistic.unchecked
To determine if the estimates have been padded.unchecked
To determine if the stakeholders should be involved.
2. What is true of risks associated with leveling resources? (You may select more than one answer. Single click the box with the question mark to produce a check mark for a correct answer and double click the box with the question mark to empty the box for a wrong answer.)
Flexibility is decreased.unchecked
Risk of delay is increased.unchecked
Slack is increased.unchecked
Total slack is decreased but free slack is increased.unchecked
The project may run out of time before it runs out of resources.