On March 1, 2014, Pechstein Construction Company contracted to construct a factory building for Fabrik Manufacturing Inc. for a total contract price of $8,118,000. The building was completed by October 31, 2016. The annual contract costs incurred, estimated costs to complete the contract, and accumulated billings to Fabrik for 2014, 2015, and 2016 are given below.
2014 2015 2016
Contract costs incurred during the year $2,867,040 $2,675,520 $2,155,440
Estimated costs to complete 3,648,960 2,155,440 -0-
Bilings to Fabrik during the year 2,790,000 3,042,000 2,286,000
A. Using the percentage-of-completion method, prepare schedules to compute the profit or loss to be recognized as a result of this contract for the years ended December 31, 2014, 2015, and 2016.
B. Using the completed-contract method, prepare schedules to compute the profit or loss to be recognized as a result of this contract for the years ended December 31, 2014, 2015, and 2016.
Compute the realized gross profit for each of the years
: Presented below is summarized information for Johnston Co., which sells merchandise on the installment basis. Compute the realized gross profit for each of the years 2014, 2015, and 2016. Prepare in journal form all entries required in 2016, applying..
|
Segmented income statement in the contribution format
: Golfpro Corporation produces and markets two types’ drivers: Model X2 and Model X3. The following data were gathered on activities last month: Prepare a segmented income statement in the contribution format for last month.
|
Other safety-related measures that affect the workplace
: As you may have recently heard, lately we received news from the corporate headquarters of the company that it would be in the best interest of the entire company to pay more attention to matters of preventing accidents and any other safety-related m..
|
Describe how foods are used within islam
: Describe how foods are used within ISLAM
|
Using the percentage-of-completion method
: On March 1, 2014, Pechstein Construction Company contracted to construct a factory building for Fabrik Manufacturing Inc. for a total contract price of $8,118,000. The building was completed by October 31, 2016. Using the percentage-of-completion met..
|
Joint tenancy with right of survivorship
: In connection with this assignment, you may want to research the legal concepts and incorporate what you find in your thread if you consider them relevant:
|
Adjustment for any underapplied or overapplied overhead
: Aerobars Inc. uses a job-order costing in which any under applied or over applied overhead is closed out to cost of goods sold at the end of the month. The company's cost of goods manufactured for March was $167,000; Determine the cost of goods sold ..
|
A very old man with enormous wings
: Read "A Very Old Man with Enormous Wings" by Gabriel García Márquez (in the course textbook and attached below). Reflect and respond to the story in a 3- to 4-page reader-response essay. Remember that reader-response essays are less formal than other..
|
Bending moments and vertical reactions
: Determine the bending moments and vertical reactions at the supports and sketch the BM and SF diagrams.
|