Reference no: EM132261516
1. Which of the following is a disadvantage of a projectized organization?
High complexity
Poor integration
It is expensive
Longer project duration
Lack of focus on the project
2. Which of the following activities is NOT considered a project?
Preparing the site for the Olympic Games
Developing a new software program
Production of automobile tires
Designing a space station
Developing a new advertising program
3. In the ________ stage of the project life cycle, a major portion of the physical project work performed.
Identifying
Defining
Planning
Executing
Closing
4. Why do project managers need to understand their organization's mission and strategy?
It is only important for senior management to understand the organization's mission and strategy
To get their job done and increase opportunities for promotion
So they can make appropriate decisions and adjustments and be effective project advocates
To reduce project duration and increase the number of projects implemented
So that they can make sure the customer is satisfied