Total revenue generated by product

Assignment Help Project Management
Reference no: EM131542528

Part I

The Sompter Meter Company has improved its production planning schedule and would like to go this over with you from a financial standpoint. The four products are made and their costs are shown below:

Product

Raw Material Cost

Price

Minimum Demand

Maximum Demand

($/Unit)

($/Unit)

(Units per Month)

(Units per Month)

Product A

$1.20

$8.00

500

800

Product B

$2.50

$12.00

250

400

Product C

$3.50

$25.00

50

100

Product D

$4.50

$30.00

30

50

The time taken to make each product is also shown below:

Time Taken for Assembly

Product A

3

mins/unit

Product B

6

mins/unit

Product C

15

mins/unit

Product D

18

mins/unit

Monthly Overhead costs as well as the number of workers in the facility and their hourly pay rates are given in the following table below:

Overhead Costs (Monthly)

Number of Workers

Hourly Payrate

$5,000.00

3

$12.00

The production plan calls for product A -700, B-350, C-80 and D-42 to be made. Calculate the following using the traditional method of accounting:
A. How long does it take for each product to be made based on the production plan?
B. Raw Material Cost per product?
C. Labor Costs of Plan per product?
D. Allocated overhead costs per product? (Please use the fractional labor hours here to determine this)
E. Total cost per product?
F. Total revenue generated by product?
G. Profit per product?
H. Unit Profit per product?
I. Total Profit Generated by production plan?

Part II
Activity Based Costing

The overhead cost is now being allocated based on the following table below:

Category

Plant and Equipment

Management

Purchasing

Sales and Shipping

Total Cost

$700.00

$2,200.00

$600.00

$1,500.00

Cost Allocation

 Square feet

 Labor hours

Purchase orders

Customer orders

Total units used

10000

2400

130

91

Product A

1000

500

10

5

Product B

2000

450

35

20

Product C

3000

690

60

41

Product D

4000

760

25

25

Determine the following based on the original production plan (product A -700, B-350, C-80 and D-42):
A. Plan and equipment cost per product?
B. Management costs per product?
C. Purchasing Costs?
D. Sales and shipping cost?
E. Total allocated overhead cost?
F. Profit per product?
G. Unit profit per product?
H. Total Profit of production plan?

I. Do you have any suggestions for the Sompter Meter Company's production plan?

Reference no: EM131542528

Questions Cloud

Example of a recent business situation : Give an example of a recent business situation that illustrates justice being served (or not). In light of the role of HR in perpetuating workplace ethics
Find the market demand and inverse demand equations : Find the market demand and inverse demand equations. Find the price elasticity of demand and the marginal revenue equation.
Examine the regulatory agencies : Examine the regulatory agencies related to your chosen environmental agent? What is the role of these agencies
Dispute and how the court resolved the dispute : In your own words, summarize the case and discuss the nature of the dispute and how the court resolved the dispute.
Total revenue generated by product : How long does it take for each product to be made based on the production plan? B. Raw Material Cost per product - Total revenue generated by product
Progress reports are critical in monitoring progress : During the weekly reporting, one person gives the status of an 8-day task as 50% complete and 5 days remaining on the work.
Two statutory references for this law : What is the name of the federal statute that gives the government the right to get a price adjustment in this case?
Discuss the french revolutionaries : Please choose one of the following questions to answer for this week's assignment. When you respond to your fellow classmates this week, please choose someone.
Why is this stuff so important : Why is this stuff so important? If you use anything outside of your thoughts; I will need a reference or citation within your paper.

Reviews

Write a Review

Project Management Questions & Answers

  Create a project schedule and align resources

Create a project schedule and align resources, Analyze project schedule and resource allocation

  Managerial roles and gap analysis

Write a report on Managerial Roles and Gap Analysis

  Questionaire on project management

Questionaire on Project Management

  Describe the market growth rate for product

Describe the market growth rate for product and service.

  Prepare a work plan and project schedule - gantt chart

Design an online system for the human resources department to manage available job positions.

  Project risk management approach

How does a project risk management approach pro-vide an early warning signal for impending problems or issues

  Black-scholes options pricing model

Calculate the payoff and the profits for investments

  Describe the features or characteristics of product

Describe the features or characteristics of your product or service.

  Write paper on inventory management system

Write paper on Inventory Management System.

  Analysis of the overall project risk

Analysis of the overall project risk

  Investment and performance analysis

Evaluate the usefulness of ROCE

  Distribution strategy and project management

Distribution strategy and project management

Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd