Total cost of the excavation activity for this building

Assignment Help Operation Management
Reference no: EM131429468

A new hospital building is to be constructed in Athens, Ohio. The design plans indicate that the building will be of 400 feet long by 225 feet wide. The building includes a basement and subgrade that will be, on average, 14 feet below the existing ground. The contractor plans to use two excavation crews for this project and each crew can excavate 165 cubic yards of material per hour. If the cost for each crew is $ 150 per hour, what is the total duration (in days) and total cost of the excavation activity for this building? Assume an 8-hour workday.

Reference no: EM131429468

Questions Cloud

Same mean unconfined compressive strength of core : Evaluate whether both proposed designs would achieve the same mean unconfined compressive strength of core (in psi) or not at .05 under equal (σ12=σ22) *AND* unequal (σ12≠σ22) variance assumptions.
Human resource information system facilitate : How can a human resource information system (HRIS) facilitate and organization's evaluation of the success or failure of its change process? Determine what ethics will guide you throughout your organizational career.
How will systems receive ip addresses : Linx, LLC. has a new research and development group - LSDG. All systems in LSDG will run the Linux operating system and will access resources, as well as share resources, with Linx, LLC.'s Microsoft Active Directory domain. The domain consists of ..
Classify the differentiating factor of this new coolant : A new machine coolant product has an improved formula that enables it to more effectively prevent a machine from overheating than its next closest substitute. (a) Classify the differentiating factor of this new coolant into the appropriate cell of th..
Total cost of the excavation activity for this building : A new hospital building is to be constructed in Athens, Ohio. The design plans indicate that the building will be of 400 feet long by 225 feet wide. The building includes a basement and subgrade that will be, on average, 14 feet below the existing gr..
Write the speech for a specific target audience : "Alcohol and drug abuse are associated with crime on the streets, health problems, the breakdown of the family, and poor job performance. Identify and solve the problem..."Create a campaign speech that employs creative, innovative strategies to bot..
Score in the original distribution : A distribution with m = 35 and s = 8 is being standardized so that the new mean and standard deviation will be m = 50 and s = 10. In the new, standardized distribution, your score is X = 45. What was your score in the original distribution?
When have others conflicts of interest impacted : When have others’ conflicts of interest impacted how you or those you know were treated? Why do you believe conflicts of interest are so pervasive in society? Why don’t we take more steps to avoid them? Why is it so hard for individuals to recognize ..
Discuss the importance of communication : Discuss the importance of communication and information exchange to project success. What are the crucial features and elements of effective communication and information exchange in successful projects?

Reviews

Write a Review

Operation Management Questions & Answers

  Speculative risk assessment and predictable loss coverage

Kilmetric Subsidies, a sub-agency of the United Nations Agricultural Outreach Program employs Host Country Agents to monitor disbursement of grant money to local villages and regional governments to insure that funds are used in a cost effective mann..

  Is leadership just another word for influence

Some people say it dilutes a leader’s authority if subordinates are allowed to give feedback to the leader concerning their perceptions of the leader’s performance. Do you agree? Is leadership just another word for influence? Can you think of some ex..

  The risks of strategic alliances often include

The risks of strategic alliances often include all of the following EXCEPT:

  Manufacturing plus assembly

Last month Silver Star used a total of 4,000 hours of labor. Its labor relations policy will not allow the combined total hours of labor (Manufacturing plus assembly) to increase or decrease by more than 500 hours from month to month. Silver Star wou..

  Value of pearson coefficient of skegness for distribution

What is the value of the Pearson coefficient of Skegness for a distribution with a mean of 17, median of 13 and standard deviation of 7?

  Explain the basic tools for projecting personnel needs

What is workforce planning? Explain the basic tools for projecting personnel needs (labor demand).

  Explain how many workers will you fire in march

Assume chase policy is being used, that is, the number of workers is changed every month to match demand with capacity. Explain how many workers will you fire in March.

  Describe the four costs of quality

Describe the four costs of quality. Explain what each cost is and the two that every operations manager must omit from daily operations. Defend your response with examples.

  Bright-eyed and bushy-tailed inside salesman

As sales manager, you have noticed changes in salesman Mike lately. Mike used to be your “bright-eyed and bushy-tailed inside salesman,” but now he seems tired all the time. You even caught him asleep at his desk twice in the last week. You are sorry..

  Create a massage for business communication

Like other large airlines, Global Airlines has a points-based incentive program. Customers who who join Global's FreeMiles program earn points by purchasing tickets from Global or by using their member number.

  What was the first computer that bill gates and paul allen

What was the first computer that Bill Gates and Paul Allen tried to write software for? What did they write?

  What is supply chain total for each stock level

Supply chain total for each stock level. Fill rates for each stock level. Illustrate what would you choose also why (describe in detail).

Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd