Reference no: EM132267957
Questions Six Sigma Yellow Belt - Assessment
1. Tool used to map High level Process
A. Pie Chart
B. Histogram
C. Process flow Chart
D. Pareto
E. PFMEA
2. ______ is an improvement process in which a company measures its performance against that standards and uses the information to improve its own performance.
A. Cause and Effect Diagram
B. Control Chart
C. Benchmarking
D. Six Sigma
3. Once mitigation action on FMEA has been taken the RPN should ______.
A. flactuate
B. reduce
C. increase
D. remain same
4. Measuring downtime of an application is an example of:
I: Discrete data
II: Continuous data
A. I only
B. II only
C. Both I and II
D. Neither I nor II
5. In the measurement of distance between 2 points, which of the following factors is LEAST likely to be influenced by the person making the measure?
A. Precision of measurement
B. True distance between two points.
C. Calibration of measurement
D. Accuracy of measurement
6. Which of this is NOT a correct statement?
A. If DPMO increases, Sigma Level goes down
B. None of the listed options
C. If Yield increases, Defect Rate goes down
D. If Process Mean shifts towards Target, Yield decreases
E. If variation increases, Sigma Level goes down
7. Your choice of VOC tool depends on which of the following factor(s)?
A. Size of Population
B. All of the listed options
C. Money
D. Time constraints
8. Which of the following statement is True?
A. Process analyst reveals the utilization of time & resource by the process
B. Process analysis allows deep investigation into the process
C. Process analysis helps in finding out redundancies, inefficiencies, bottlenecks & delays
D. All of the listed options
9. Which of the following is the correct objective of sampling?
A. II only
B. I only
C. Neither I nor II
D. Both I and II
10. The goal of a six sigma program is to make the process
A. more standardized
B. Next generation
C. Cross functional
D. more Automated
E. Capable & Stable