There may be more than one critical path in project network

Assignment Help Operation Management
Reference no: EM131034909

Which one of the following statements is ?false?

A. There may be more than one critical path in a project network.

B. The critical path is the sequence of activities between a? project's start and finish that takes the shortest time to complete.

C. If one of the activities on the critical path is? delayed, the entire project will be delayed.

D. The activities along the critical path determine the completion time of the project

Reference no: EM131034909

Questions Cloud

The superbowl champion of next year : Who in your economic model do you predict to be the superbowl champion of next year
Wehane and radin argue what exactly : "Employment at Will and Due Process," Wehane and Radin argue what exactly? What's their main conclusion, what are the crucial parts of their argument in support of that conclusion? Make sure you cite the article at least 4 times in footnotes. Word..
The detriment of your marketplace performance : Henry Mintzberg, one of the most prominent thought-leaders in Management today, proposes that the best strategies are often "emergent" in nature, meaning that they were not originally planned but born out of accident or some other fortuate deviation...
Describe the business cycle and its primary phases : Describe the business cycle and its primary phases.
There may be more than one critical path in project network : There may be more than one critical path in a project network. The critical path is the sequence of activities between a? project's start and finish that takes the shortest time to complete. If one of the activities on the critical path is? delayed, ..
Compute the present value of the refunding : Compute the present value of the refunding, using the after-tax rate on the new bonds as the discount rate. Is the refunding worthwhile?
What does the marginal physical product : Refer to the table. What does the marginal physical product equal when the amount of labor goes from 11 to 12 units?
Which financial management practices are most effective : Discuss which financial management practices are most effective in creating and monitoring an operating budget/Relating to Health Care
What factors drive benefits of influenza pandemic stockpile : What factors drive the benefits of influenza pandemic stockpile? the costs? How should Roche think about setting inventory, production, and capacity targets? How can Roche keep their supply chain network alive? Should it?

Reviews

Write a Review

Operation Management Questions & Answers

  Book review - the goal

Operations Management is about a book review. Title of the book is "Goal". This book has been written by Dr. Eliyahu Goldartt. The book has been appreciated by many as one of those books which offers an insight into the operations and strategic capac..

  Operational plan in hospitality enterprise

Operational plan pertaining to a hospitality enterprise is given in detail in the solution. The operational plan is an important plan or preparation which gives guidelines regarding the role and responsibilities of each and every operation at all lev..

  Managing operations and information

Recognise the importance of a strategic approach to the development and deployment of organisational information systems. Demonstrate an understanding of the importance of databases and their integration to the organisation's overall information mana..

  A make-or-buy analysis

An analysis of the holding costs, including the appropriate annual holding cost rate.

  Evolution and contributor of operations management

Briefly explain Evolution and contributor of Operations management.

  Functions and responsibilities of an operations manager

A number of drivers of change have transformed the roles, functions and responsibilities of an operations manager over recent years. These drivers have not only been based on technological innovations but also on the need for organisations to develop..

  Compute the optimal order quantity

Compute the Optimal Order quantity of DVD players. Determine the appropriate reorder point.

  Relationship to operations practice in the organisation

Evaluate problems in operations and identify approaches to overcoming them. Critically evaluate operating plans and identify areas for improvement. Justify, implement and evaluate changes to operations in line with modern approaches.

  A make or buy analysis

Develop a report for Figi Fabricating that will address the question of whether the company should continue to purchase the part from the supplier or begin to produce the part itself.

  Prepare a staffing plan

Prepare a staffing plan showing the change of your unit from medical/surgical staffing to oncology staffing.

  Leadership styles in different organizations

Ccompare the effectiveness of different leadership styles in different organizations

  Risk management tools and models

Be able to understand the concept of risk, roles and responsibilities for risk management and risk management tools and models.

Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd