You are the sponsor for project XY. The project manager has provided you the following three status reports. The project started on 2/1 and it is now the end of the 4th week. For this assignment, complete this packet in its entirety to include all tables, blanks, and questions. Complete the file and submit as your completed assignment.
Percent: Completion Report
Activity
Date Started
Percent completed
Time to Complete (weeks)
AB
2/1
100
Completed
AC
2/8 (Approved delay, 1 week)
40
3
AD
DE
Not started-unapproved delay
0
2
BF
2/14
Project Planning Budget: Dollars Budgeted Per Week for Each Activity, Project Starting 2/1
Week 1
Week 2
Week 3
Week 4
Week 5
Week 6
Week 7
Week 8
Total $
2,000
6,000
3,000
4,000
5,000
20,000
2,500
7,500
15,000
CE
3,500
10,500
EF
Total:
7,000
9,000
8,500
9,500
11,500
10,000
64,500
Cost Summary
Week Ending
Cumulative to Date
Budget Cost
Actual
(Over) / Under
6000
6200
(200)
6,200
4,500
(500)
11,000
2,400
(2,400)
7500
7,400
2,800
(800)
(2,500)
--
3500
Total
9,700
34,000
30,600
3,400
It is now the end of Week 4 and you want to determine the status of the project using earned value management. Complete the table and earned value metrics below. Some of the information has already been entered for you.
% Complete
Planned Value (PV)
Earned Value (EV)
Actual Cost (AC)
Cost Variance
Schedule Variance
Total Budget
60
8,000
1000
25
n/a
DE*
TOTAL
* Note that activity AC was delayed one week (approved);
DE is one week behind schedule (not approved).
Calculate each of the following:
Cost Variance ($) = EV - AC
Schedule Variance ($) = EV - PV
Schedule Variance (weeks) = Schedule Variance ($) / Average Weekly PV
Cost-at-Completion= (Rate of Spending x Total Budget) = ([AC / EV] * Total Budget)
CPI = EV / AC
SPI = EV / PV
Add your written analysis below by answering three questions:1. What is the state of the project?2. Which activity has had the most positive impact on the project?3. Which activity has had the most negative impact on the project?
Learning contract proposal that will form the basis of your learning contract report.
"Change is the only constant " Evaluate the different types of change that have occurred in Sony.
How do advertisers try to use group influence? Will you find any specific examples and explain the relevant theory of group behavior and influence?
You have been appointed by Sony as a consultant on change management. Advise Sony on how they could implement the change by using the various theories of change you have learnt.
The purpose of this project is to help you to gain an understanding of how the stock market works and of the relationship between theory and practice.
Find not only the optimal production quantities, but also the optimal total cost.
Describe the management process and identify the skills required to manage business organizations.
Case Study : Bert's Bonsai and Aquatic Sport Museum Prepare a knowledge management system.
Demonstrate understanding of the many-sided nature of knowledge management
Write a paper on Historical Trends of Management.
Theory of Planned Behavior and Integrated Behaviors Model
Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!
whatsapp: +1-415-670-9521
Phone: +1-415-670-9521
Email: [email protected]
All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd