1. What is the primary purpose of work breakdown structure in project management?

a) It illustrates the hierarchial organization of all activities in the project.

b) It shows the start and finish times for each activity in the project.

c) It shows the estimate for each activity duration when the exact activity time is not certain.

d) It is a graphical time table showing the durations and precedence relationships among the activities in the project.

e) It provides the same scheduling information as shown in Gantt Chart.

2. The slack of an activity in project scheduling is:

a) The maximum amount of time needed to complete an activity.

b) The minimum amount of time needed to complete an activity.

c) The maximum amount of time an activity can be delayed without affecting the project completion time.

d) An indicator of the flexibility in the scheduling of this activity.

e) Both C and D are correct.

3. Which of the following is NOT an advantage of using a matrix project team?

a) Improved communication between functional divisions.

b) Team members have a functional home after the completion of project.

c) Corporate goal can be followed due to direct interactions among the various departments.

d) The project manager has full authority and control over the project; team members only need to follow the orders from the project manager and not from the functional departments.

e) The combined functional knowledge of employees from different functional areas can be used to create synergistic solutions to problems as they arise over the duration of the project.

4. As a project manager, you need to deal with many people issues as well as scheduling of activities. Which of the following project organizational structures would not require your time and attention to handle team members' frustation on dealing with two bosses, potential conflict of interests among departments, and team members' resistance to working on tasks outside their areas of expertise? Team members are also very hesitant on collaboration with coworkers from other divisions.

a) Pure project structure.

b) Matrix project structure.

c) Functional project structure.

d) Hierarchical project structure.

e) Both matrix and pure project structures are acceptable and fulfill the required criteria.

5. An organization using pure project team would be more likely, than organizations using other configurations of project teams, to receive complaints about:

a) A lack of motivation and devotion on the part of team members.

b) Long and involved lines of communication.

c) The frustration of reporting to two bosses.

d) The lack of functional home after completion of the project.

e) Conflict between the project manager and department heads.

Reference no: EM131673521

Questions Cloud

Calculate total variable labor cost for the year : Using High-Low to Calculate Predicted Total Variable Cost and Total Cost for a Time Period that Differs from the Data Period Refer to the information for Pizza.
What type of internal organizational structure : What type of internal organizational structure is currently implemented within the organization? How does this structure impede or promote innovation?
Explain the strengths and weaknesses of the approach : Explain the strengths and weaknesses of the approach and what might be done differently using the Fabrics Inc. example. Identify the sources of data used.
Explain what einstein meant in this statement : "Innovation is not the product of logical thought, although the result is tied to logical structure." Explain what Einstein meant in this statement.
The slack of activity in project scheduling : What is the primary purpose of work breakdown structure in project management? The slack of an activity in project scheduling is:
Discuss the fair market value of comparable housing : Tim is the vice president of western operations for Maroon Oil Company and is stationed in San Francisco. He is required to live in an employer-owned home.
Summarize how to conduct a proper investigation of claims : What change(s) would you make to minimize future occurrences of these violations? Summarize how to conduct a proper investigation of these claims.
Integrity organization and compliance organization : differences between an "integrity organization" and a "compliance organization" in the approach of a firm to organizational ethics?
Role of the product champion in bringing a new product : What is the role of the product champion in bringing a new product or service into existence in a corporation?

Reviews

Write a Review

Operation Management Questions & Answers

  Book review - the goal

Operations Management is about a book review. Title of the book is "Goal". This book has been written by Dr. Eliyahu Goldartt. The book has been appreciated by many as one of those books which offers an insight into the operations and strategic capac..

  Operational plan in hospitality enterprise

Operational plan pertaining to a hospitality enterprise is given in detail in the solution. The operational plan is an important plan or preparation which gives guidelines regarding the role and responsibilities of each and every operation at all lev..

  Managing operations and information

Recognise the importance of a strategic approach to the development and deployment of organisational information systems. Demonstrate an understanding of the importance of databases and their integration to the organisation's overall information mana..

  A make-or-buy analysis

An analysis of the holding costs, including the appropriate annual holding cost rate.

  Evolution and contributor of operations management

Briefly explain Evolution and contributor of Operations management.

  Functions and responsibilities of an operations manager

A number of drivers of change have transformed the roles, functions and responsibilities of an operations manager over recent years. These drivers have not only been based on technological innovations but also on the need for organisations to develop..

  Compute the optimal order quantity

Compute the Optimal Order quantity of DVD players. Determine the appropriate reorder point.

  Relationship to operations practice in the organisation

Evaluate problems in operations and identify approaches to overcoming them. Critically evaluate operating plans and identify areas for improvement. Justify, implement and evaluate changes to operations in line with modern approaches.

  A make or buy analysis

Develop a report for Figi Fabricating that will address the question of whether the company should continue to purchase the part from the supplier or begin to produce the part itself.

  Prepare a staffing plan

Prepare a staffing plan showing the change of your unit from medical/surgical staffing to oncology staffing.

  Leadership styles in different organizations

Ccompare the effectiveness of different leadership styles in different organizations

  Risk management tools and models

Be able to understand the concept of risk, roles and responsibilities for risk management and risk management tools and models.

Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd