The rig shown consists of a 1200-lb horizontal member abc

Assignment Help Civil Engineering
Reference no: EM13384342

The rig shown consists of a 1200-lb horizontal member ABC and a vertical member DBE welded together at B. The rig is being used to raise a 3600-lb crate at a distance x=12 ft from the vertical member DBE.If the tension in the cable is 4 kips, determine the reaction at E assuming (a) anchored at F as shown in the figure, (b) attached to the vertical member at a point located 1 ft above E. 

Reference no: EM13384342

Questions Cloud

A beam is made by bonding a brass core to a steel tube and : a beam is made by bonding a brass core to a steel tube and is subjected to a bending moment as shown. knowing that b
Nbspwhen titrating 015 m hcl with a calcium hydroxide : nbspwhen titrating 0.15 m hcl with a calcium hydroxide solution of unknown concentration 35 ml of acid are required to
An aqueous vinegar sample contains 44 acetic acid by mass : an aqueous vinegar sample contains 4.4 acetic acid by mass and has a density of 1.006 gml. calculate the amount of
A chemist dissolves 09 g of an unknown monoprotic one : a chemist dissolves 0.9 g of an unknown monoprotic one acidic h acid in water. she finds that 14.6 ml of 0.426 m naoh
The rig shown consists of a 1200-lb horizontal member abc : the rig shown consists of a 1200-lb horizontal member abc and a vertical member dbe welded together at b. the rig is
A2500-ml sample of propionic acid ch3ch2cooh of unknown : a 25.00-ml sample of propionic acid ch3ch2cooh of unknown concentration was titrated with 0.104 m koh. the equivalence
After balancing of the equation for the reaction under : after balancing of the equation for the reaction under basic conditionsbi2o3s ocl-aq --gt cl-aq bio3-aqwhat is the
It is required to dewater a construction site 80 m by 80 m : it is required to dewater a construction site 80 m by 80 m. the bottom of the construction will be 1.5 m below the
The second-order reaction 2 mnco5 mn2co10 has a rate : the second-order reaction 2 mnco5 mn2co10 has a rate constant equal to 3.0 x 109 m-1 s-1 at 25degc. if the initial

Reviews

Write a Review

Civil Engineering Questions & Answers

  Explain how to draw v-t and x-t curves of industrial planer

The velocity of the bed is limited to a maximum value of 150 mm/s to the right and 300 mm/s to the left; the acceleration is successively equal to 150 mm/s^2 to the right, zero 150 mm/s^2 to the left, zero, etc.

  Surface overflow rate-horizontal flow through velocity

A rectangular clarifier with a length:width ratio of 3:1 receives a flow of 850m3/day. the clarifiers depth is 4.0m and the detention time of the water inthe clarifier is 2.4 hrs, what are the surface overflow rate and the horizontal flow through ..

  Explain how to estimate the long-term safety factors

A 2.0m-wide strip at a depth of 1 m in a stiff clay carries a wall load of 425 kN/m. The saturated unit weight of the caly is 20kN/m^3. TRiaixal tests give the following results: c'=10 kPa, phi'=28 degree, cu=105kPa, and phi_u = 0.

  Prepare a capstone report

Prepare a capstone report for designing of steel building using AISC 14 edition manual.

  Determining equivalency factor of single axle

The weights on the same axles when the truck is empty and leaving the power plant are 10 kips, 12 kips, and 8 kips, respectively. A two lane road is to be designed to serve the power plant and to last for a period of 10 years. a) What is the equiv..

  Determine what was the intensity of the erthquaker

A city near the epicenter of an earthquake sustains major damage to poorly constructed building, althought hospital and schools designed to resist dmage from ground motion sustsain only minor damage.

  Calculate the maximum tensile load in n

Consider a cold worked C11000 copper alloy rod 21 mm in diameter and 250 mm in length. Calculate (a) the maximum tensile load, in N, and (b) the maximum length, in mm, to which the rod may be stretched without plastic deformation.

  Compute 95 percent confidence intercals for b0 and b1

An article reports measurements of expansion for several concrete bridges in the area of Quebec City. Following are measurements of horizontal and vertical expansion (in parts per hundred thousand) for several locations

  Calculate percipitable water in standard atmoshperic column

Calculate the percipitable water (mm) in a 10-km high standard atmoshperic column if the surface conditions are temperature=20 degrees C, pressure=101.3 kPa and the laspe rate is 6.5 degrees C/km.

  What is its depth in the 18 inch diamenter pipeline

Sewage flows through a 12" diameter pipeline then through an 18" diamenter pipeline. The flow is the same (unknown) value in each pipe, and the slope is the same (unknown) contant value for both pipes.

  Calculate the bearing stress on the shaft key

A rotating shaft with an applied torque of 400 Newton-meters is held in place (stopped) by a shaft key. The diameter of the shaft is 15 centimeters. The shaft key has a length of 20 cm, and is square, with its width and height being 5 cm.

  Compute the stresses and deflections at the corner of slab

Compute the stresses and deflections at the corner of the slab according to Westergaard and Ioannides. Compute the stresses and deflections at the edge and interior according to Westergaard.

Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd